HOTLINE
702-293-NEON (6366)

Traffic Alerts Archive

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, AS OF JANUARY 13:

  Location Date Time of Day Details
US 95 (515) NB near

Spaghetti Bowl

Ongoing – 2/10 24/7 Left lane closed on US 95 (I-515) northbound, Las Vegas Blvd to Spaghetti Bowl
Ongoing – 2/10

9pm – 6am

Night Northbound US 95, Las Vegas Blvd to Spaghetti Bowl, restricted to one lane of through traffic
Pinto Ln Ongoing – 2/9 24/7 Road Closure: Pinto Ln closed between Desert Ln and MLK Blvd

Alternate access available for local traffic only.

Casino Center Blvd

On-Ramp to US 95 NB

1/13, 16, 17 and

1/30 – 2/10

Night Ramp Closure: Casino Ctr on-ramp to US 95 (515) NB closed. Follow posted detours.
US 95 NB/SB, Decatur Blvd to Rancho Dr 1/16 – 1/20 Night US 95 HOV lanes closed northbound and southbound, Decatur Blvd to Rancho Dr
US 95: Rancho Dr to Spaghetti Bowl Ongoing – 1/20 Night Lane restrictions on US 95 in both directions between Rancho Dr and the Spaghetti Bowl
I-15 NB Off-Ramp to Charleston Blvd WB 1/18 Night I-15 northbound off-ramp to Charleston Blvd westbound rerouted to Iron Horse Ct
Desert Ln Ongoing – 2/9 24/7 Desert Ln restricted to local traffic only between Alta Dr and Hastings Ave
1/16 – 1/18 Day Lane restrictions on Desert Ln, Alta Dr to Pinto Ln
Grand Central Pkwy 1/13 Night Lane restrictions on Grand Central Pkwy in both directions, Iron Horse Ct to Charleston Blvd
Permanent – 2019 Night Sidewalk closed on southbound Grand Central Pkwy, Iron Horse Ct to Charleston Blvd
Charmast Ln 1/17 – 1/20 Day Lane restrictions on Charmast Ln from Richard Ct to Ellis Ave
Wyoming Ave 1/20 Night Lane restrictions on Wyoming Ave between Industrial Rd and Fairfield Ave
Bonanza Rd /

Casino Center Blvd

Ongoing Day Lane restrictions on eastbound Bonanza Rd near Casino Center Blvd
Lane restrictions on southbound Casino Center Blvd from Bonanza Rd to US 95
Alta Dr/MLK Blvd Ongoing 24/7 Lane restrictions on Alta Dr, between MLK Blvd and Shadow Ln
Night Lane restrictions on MLK Blvd at Alta Dr
Charleston Blvd Ongoing Night Lane restrictions on Charleston Blvd, between Shadow Ln and I-15
MLK Blvd/US 95 Ongoing – 2/23 24/7 Intermittent lane restrictions on MLK Blvd northbound at US 95
MLK Blvd/Oakey Blvd Ongoing Day Lane restrictions on MLK Blvd, Wall St to Oakey Blvd
Lane restrictions on Oakey Blvd near MLK Blvd. Follow posted detours. Officer assistance.
Shadow Ln Ongoing Night Lane restrictions on Shadow Ln, between Charleston Blvd and Ellis Ave
Ellis Ave Ongoing Day Lane restrictions on Ellis Ave, between Shadow Ln and Desert Ln

 

Major Spaghetti Bowl Ramp Closures / Detours – Use Alternate Routes When Possible
I-15 to US 95 N Ramps
I-15 SB to US 95 NB Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 South to US 95 North CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound then turn south on MLK Blvd for access to US 95 North.
I-15 NB to US 95 NB Ongoing –

Feb 2017

24/7 Ramp Rerouted: Ramp from I-15 North to US 95 North detoured onto the MLK Blvd exit ramp and back onto US 95 North via a temporary detour. Reduced speed, one lane.
NB MLK Off-Ramp
US 95 NB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from US 95 North to MLK Blvd CLOSED. Detour: Traffic will continue on US 95 North to Rancho Dr and turn around on US 95 South to exit at MLK Blvd.
I-15 NB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 North to MLK Blvd CLOSED. Detour: Traffic will exit Charleston Blvd westbound and turn north to access MLK Blvd.
I-15 SB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 South to MLK Blvd CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound to access MLK Blvd.

Upcoming Work

Location Date Time of Day Details
US 95 NB/SB, Decatur Blvd to Rancho Dr 1/23 – 3/31 24/7 US 95 HOV lanes closed northbound and southbound, Decatur Blvd to Rancho Dr
Night Intermittent closure of left lane on US 95 northbound, Rancho Dr to Decatur Blvd
I-15 NB at Spring Mtn/Desert Inn TBD Night Right lane of I-15 northbound closed at Spring Mountain Rd
Right lane of I-15 northbound closed at Desert Inn Rd

Night work hours are generally 7pm – 5am                             Dates and times subject to change due to weather and field conditions.

 

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, AS OF JANUARY 6:

       Location Date Time of Day Details
US 95 (515) NB/SB near

Spaghetti Bowl

Ongoing – 2/23 24/7 Left lane closed on US 95 (I-515) northbound, Las Vegas Blvd to Spaghetti Bowl
1/4 – 1/6

1/9 – 1/13

9 pm – 6 am

Night Northbound US 95, Las Vegas Blvd to Spaghetti Bowl, restricted to one lane of through traffic
Southbound US 95, MLK Blvd to Casino Center Blvd, restricted to one lane of through traffic
MLK Blvd at US 95 1/10 at 7pm –

1/11 at 6am

11 hrs Road Closure: MLK Blvd closed in both directions, Bonanza Rd to southbound US 95
MLK Blvd on-ramp

to US 95 NB

Ramp Closure: MLK Blvd on-ramp to US 95 northbound closed
Casino Center Blvd On-Ramp to US 95 NB 1/12, 13, 16 and

1/30 – 2/10

Night Ramp Closure: Casino Ctr on-ramp to US 95 (515) NB closed. Follow posted detours.
Pinto Ln 1/9 – 2/9 24/7 Road Closure: Pinto Ln closed between Desert Ln and MLK Blvd.

Alternate access available for local traffic only.

US 95: Rancho Dr to Spaghetti Bowl Ongoing – 1/16 Night Lane restrictions on US 95 in both directions between Rancho Dr and the Spaghetti Bowl
Desert Ln 1/6 – 1/13 Day Lane restrictions on Desert Ln, Alta Dr to Pinto Ln
1/9 – 2/9 24/7 Desert Ln restricted to local traffic only between Alta Dr and Hastings Ave.
Grand Central Pkwy/Charleston Blvd 1/9 – 1/13 Night Lane restrictions on Grand Central Pkwy between LV Premium Outlet Dr and Charleston Blvd
Lane restrictions on Charleston Blvd at Grand Central Pkwy/Western Ave
I-15 NB at Spring Mtn/Desert Inn 1/10 Night Right lane of I-15 northbound closed at Spring Mountain Rd
Right lane of I-15 northbound closed at Desert Inn Rd
US 95 NB/City Pkwy 1/11 Night Right shoulder closure on US 95 (515) northbound at City Pkwy
I-15 NB near Sunset Rd 1/12 Night Right lane closed on I-15 northbound, north of Sunset Rd at UPRR bridge
I-15 SB /

Washington Street

1/13 Night Right lane on I-15 southbound closed at Washington Street exit
Left shoulder closed on ramp from I-15 southbound to US 95 southbound
Bonanza Rd /

Casino Center Blvd

Ongoing Day Lane restrictions on eastbound Bonanza Rd near Casino Center Blvd
Lane restrictions on southbound Casino Center Blvd from Bonanza Rd to US 95
Alta Dr (Bonneville Ave) /MLK Blvd Ongoing Day Lane restrictions on Alta/Bonneville, between LV Premium Outlet Dr and Shadow Ln
Night Lane restrictions on MLK Blvd at Alta Dr
Charleston Blvd Ongoing Night Lane restrictions on Charleston Blvd, between Shadow Ln and I-15
1/6 – 1/8 Adjacent project: Lane restrictions on Charleston Blvd at Commerce
MLK Blvd/US 95 Ongoing – 2/23 Night Lane restrictions on MLK Blvd northbound at US 95
MLK Blvd/Oakey Blvd Ongoing Day Lane restrictions on MLK Blvd, Wall St to Oakey Blvd
Lane restrictions on Oakey Blvd near MLK Blvd. Follow posted detours. Officer assistance.
Shadow Ln Ongoing Night Lane restrictions on Shadow Ln, between Charleston Blvd to Ellis Ave
Ellis Ave Ongoing Day Lane restrictions on Ellis Ave, Shadow Ln to Desert Ln
Major Spaghetti Bowl Ramp Closures / Detours – Use Alternate Routes When Possible
I-15 to US 95 N Ramps
I-15 SB to US 95 NB Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 South to US 95 North CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound then turn south on MLK Blvd for access to US 95 North.
I-15 NB to US 95 NB Ongoing –

Feb 2017

24/7 Ramp Rerouted: Ramp from I-15 North to US 95 North detoured onto the MLK Blvd exit ramp and back onto US 95 North via a temporary detour. Reduced speed, one lane.
NB MLK Off-Ramp
US 95 NB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from US 95 North to MLK Blvd CLOSED. Detour: Traffic will continue on US 95 North to Rancho Dr and turn around on US 95 South to exit at MLK Blvd.
I-15 NB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 North to MLK Blvd CLOSED. Detour: Traffic will exit Charleston Blvd westbound and turn north to access MLK Blvd.
I-15 SB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 South to MLK Blvd CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound to access MLK Blvd.

Upcoming Work

Location Date Time of Day Details
Wyoming Ave 1/16 Night Lane restrictions on Wyoming between Industrial and Fairfield

Night work hours are generally 7pm – 5am                             Dates and times subject to change due to weather and field conditions.

 

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, AS OF DECEMBER 30:

       Location Date Time of Day Details
Major Spaghetti Bowl Ramp Closures / Detours – Use Alternate Routes When Possible
I-15 to US 95 N Ramps
I-15 SB to US 95 NB Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 South to US 95 North CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound then turn south on MLK Blvd for access to US 95 North.
I-15 NB to US 95 NB Ongoing –

Feb 2017

24/7 Ramp Rerouted: Ramp from I-15 North to US 95 North detoured onto the MLK Blvd exit ramp and back onto US 95 North via a temporary detour. Reduced speed, one lane.
NB MLK Off-Ramp
US 95 NB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from US 95 North to MLK Blvd CLOSED. Detour: Traffic will continue on US 95 North to Rancho Dr and turn around on US 95 South to exit at MLK Blvd.
I-15 NB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 North to MLK Blvd CLOSED. Detour: Traffic will exit Charleston Blvd westbound and turn north to access MLK Blvd.
I-15 SB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 South to MLK Blvd CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound to access MLK Blvd.
Casino Center Blvd On-Ramp to US 95 NB 1/3 Night Ramp Closure: Casino Ctr on-ramp to US 95 (515) NB closed. Follow posted detours.
US 95: Rancho Dr to Spaghetti Bowl Ongoing – 1/13 Night Lane restrictions on US 95 in both directions between Rancho Dr and the Spaghetti Bowl
US 95 (515) NB/SB near

Spaghetti Bowl

Ongoing – 2/23 Night Lane restrictions on US 95 (I-515) northbound, from Las Vegas Blvd to Spaghetti Bowl
Lane restrictions on US 95 (I-515) southbound, from Spaghetti Bowl to Las Vegas Blvd
Bonanza Rd/

Casino Center Blvd

Ongoing Day Lane restrictions on eastbound Bonanza Rd near Casino Center Blvd
Lane restrictions on southbound Casino Center Blvd from Bonanza Rd to US 95
Alta Dr (Bonneville Ave) /MLK Blvd Ongoing Day Lane restrictions on Alta/Bonneville, between LV Premium Outlet Dr and Shadow Ln
Night Lane restrictions on MLK Blvd at Alta Dr
Desert Ln Ongoing Day Lane restrictions on Desert Ln, Alta Dr to Hastings Ave
Charleston Blvd Ongoing Night Lane restrictions on Charleston Blvd, between Shadow Ln and I-15
MLK Blvd/US 95 Ongoing – 2/23 Night Lane restrictions on MLK Blvd northbound at US 95
MLK Blvd/Oakey Blvd Ongoing Day Lane restrictions on MLK Blvd near Oakey Blvd. Follow posted detours. Officer assistance.
Lane restrictions on Oakey Blvd near MLK Blvd. Follow posted detours. Officer assistance.
Shadow Ln 1/3 – Ongoing Night Lane restrictions on Shadow Ln, between Charleston Blvd to Ellis Ave
Ellis Ave 1/3 – Ongoing Day Lane restrictions on Ellis Ave, Shadow Ln to Desert Ln

Upcoming Work

Location Date Time of Day Details
MLK Blvd at US 95 1/10 at 7pm –

1/11 at 6am

11 hrs Road Closure: MLK Blvd closed in both directions, Bonanza Rd to southbound US 95
MLK Blvd on-ramp

to US 95 NB

Ramp Closure: MLK Blvd on-ramp to US 95 northbound closed
Pinto Ln 1/9 – 2/9 24/7 Road Closure Pinto Ln closed between Desert Ln and MLK Blvd.

Alternate access available for local traffic only.

Desert Ln 1/9 – 2/9 24/7 Desert Ln restricted to local traffic only between Alta Dr and Hastings Ave.

Night work hours are generally 7pm – 5am                       Dates and times subject to change due to weather and field conditions.

 

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, AS OF DECEMBER 22:

    Location Date Time of Day Details
Major Spaghetti Bowl Ramp Closures / Detours – Use Alternate Routes When Possible
I-15 to US 95 N Ramps
I-15 SB to US 95 NB Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 South to US 95 North CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound then turn south on MLK Blvd for access to US 95 North.
I-15 NB to US 95 NB Ongoing –

Feb 2017

24/7 Ramp Rerouted: Ramp from I-15 North to US 95 North detoured onto the MLK Blvd exit ramp and back onto US 95 North via a temporary detour. Reduced speed, one lane.
NB MLK Off-Ramp
US 95 NB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from US 95 North to MLK Blvd CLOSED. Detour: Traffic will continue on US 95 North to Rancho Dr and turn around on US 95 South to exit at MLK Blvd.
I-15 NB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 North to MLK Blvd CLOSED. Detour: Traffic will exit Charleston Blvd westbound and turn north to access MLK Blvd.
I-15 SB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 South to MLK Blvd CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound to access MLK Blvd.
US 95: Rancho Dr to Spaghetti Bowl Ongoing – 1/13 Night Lane restrictions on US 95 in both directions between Rancho Dr and the Spaghetti Bowl
US 95 (515) NB/SB near

Spaghetti Bowl

Ongoing – 2/23 Night Lane restrictions on US 95 (I-515) northbound, from Las Vegas Blvd to Spaghetti Bowl
Lane restrictions on US 95 (I-515) southbound, from Spaghetti Bowl to Las Vegas Blvd
MLK Blvd at US 95 12/29 at 7pm –

12/30 at 6am

11 hrs Road Closure: MLK Blvd closed in both directions, Bonanza Rd to southbound US 95
MLK Blvd on-ramp

to US 95 NB

Ramp Closure: MLK Blvd on-ramp to US 95 northbound closed
Bonanza Rd/

Casino Center Blvd

Ongoing Day Lane restrictions on eastbound Bonanza Rd near Casino Center Blvd
Lane restrictions on southbound Casino Center Blvd from Bonanza Rd to US 95
Alta Dr (Bonneville Ave) /MLK Blvd Ongoing Day Lane restrictions on Alta/Bonneville, between LV Premium Outlet Dr and Shadow Ln
Night Lane restrictions on MLK Blvd at Alta Dr
Desert Ln Ongoing Day Lane restrictions on Desert Ln, Alta Dr to Hastings Ave
Charleston Blvd Ongoing Night Lane restrictions on Charleston Blvd, between Shadow Ln and I-15
MLK Blvd/US 95 Ongoing – 2/23 Night Lane restrictions on MLK Blvd northbound at US 95
MLK Blvd/Oakey Blvd Ongoing Day Lane restrictions on MLK Blvd near Oakey Blvd. Follow posted detours. Officer assistance.
Lane restrictions on Oakey Blvd near MLK Blvd. Follow posted detours. Officer assistance.
Shadow Ln 12/27 – Ongoing Night Lane restrictions on Shadow Ln, between Charleston Blvd to Ellis Ave
Ellis Ave 12/27 – Ongoing Day Lane restrictions on Ellis Ave, Shadow Ln to Desert Ln

Upcoming Work

Location Date Time of Day Details
Casino Center Blvd on-ramp to US 95 NB 1/3 Night Ramp Closure: Casino Ctr on-ramp to US 95 (515) NB closed. Follow posted detours.
Pinto Ln 1/9 – 2/9 24/7 Road Closure Pinto Ln closed between Desert Ln and MLK Blvd.

Alternate access available for local traffic only.

Desert Ln 1/9 – 2/9 24/7 Desert Ln restricted to local traffic only between Alta Dr and Hastings Ave.

Night work hours are generally 7pm – 5am                            Dates and times subject to change due to weather and field conditions.

 

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, AS OF DECEMBER 16:

    Location Date Time of Day Details
Major Spaghetti Bowl Ramp Closures / Detours – Use Alternate Routes When Possible
I-15 to US 95 N Ramps
I-15 SB to US 95 NB Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 South to US 95 North CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound then turn south on MLK Blvd for access to US 95 North.
I-15 NB to US 95 NB Ongoing –

Feb 2017

24/7 Ramp Rerouted: Ramp from I-15 North to US 95 North detoured onto the MLK Blvd exit ramp and back onto US 95 North via a temporary detour. Reduced speed, one lane.
NB MLK Off-Ramp
US 95 NB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from US 95 North to MLK Blvd CLOSED. Detour: Traffic will continue on US 95 North to Rancho Dr and turn around on US 95 South to exit at MLK Blvd.
I-15 NB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 North to MLK Blvd CLOSED. Detour: Traffic will exit Charleston Blvd westbound and turn north to access MLK Blvd.
I-15 SB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 South to MLK Blvd CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound to access MLK Blvd.
US 95: Rancho Dr to Spaghetti Bowl Ongoing  – 12/30 Night Lane restrictions on US 95 in both directions between Rancho Dr and the Spaghetti Bowl
US 95 SB/Rancho Dr Exit 12/16 and 12/19 Night Ramp Closure: US 95 southbound off-ramp to Rancho Dr closed
12/16, 18, 19 Lane restrictions on southbound Rancho Dr from US 95 to Mesquite Ave
US 95 NB/Casino Ctr 12/19 – 12/22 Night Right lane closed on US 95 (I-515) northbound near Casino Center
Lane restrictions on Casino Center on-ramp to US 95 northbound
MLK Blvd at US 95 12/20 at 7pm –

12/21 at 6am

11 hrs Road Closure: MLK Blvd closed in both directions, Bonanza Rd to southbound US 95
MLK Blvd on-ramp

to US 95 NB

Ramp Closure: MLK Blvd on-ramp to US 95 northbound closed
Grand Central Pkwy/ Charleston Blvd 12/16 Night Lane restrictions on eastbound Charleston Blvd at Grand Central Pkwy
Lane restrictions on southbound Grand Central Pkwy/Western
Bonanza Rd/Casino Ctr 12/19 – Ongoing Day Lane restrictions on eastbound Bonanza Rd near Casino Center Blvd
Lane restrictions on southbound Casino Center Blvd from Bonanza Rd to US 95
I-15 SB/Charleston 12/20 Night Right lane and shoulder restrictions on I-15 southbound at Charleston westbound off-ramp
US 95 NB near

Spaghetti Bowl

Ongoing – 2/3 Night Lane restrictions on US 95 (I-515) northbound near exit ramp to I-15 southbound
Alta Dr/MLK Blvd Ongoing Day

Night

Lane restrictions an Alta Dr, both directions between I-15 and Shadow Ln
Lane restrictions on MLK Blvd at Alta Dr
Desert Ln Ongoing Day Lane restrictions on Desert Ln, Alta Dr to Hastings Ave
Charleston Blvd Ongoing Night Lane restrictions on Charleston Blvd, both directions between Shadow Ln and I-15
MLK Blvd/US 95 Ongoing – 2/23 Night Lane restrictions on MLK Blvd northbound at US 95

Upcoming Work

Location Date Time of Day Details
MLK Blvd at US 95 12/29 at 7pm –

12/30 at 6am

11 hrs Road Closure: MLK Blvd closed in both directions between Bonanza Rd and US 95 southbound
MLK Blvd on-ramp

to US 95 NB

Ramp Closure: MLK Blvd on-ramp to US 95 northbound closed
Pinto Ln 12/27 – 1/27 24/7 Pinto Ln closed between Desert Ln and MLK Blvd. Alternate access available for local traffic only.
Desert Ln 12/27 – 1/27 24/7 Desert Ln restricted to local traffic only between Alta Dr and Hastings Ave
MLK Blvd/Oakey Blvd TBD Day Lane restrictions on MLK Blvd near Oakey Blvd. Follow posted detours. Officer assistance.
Lane restrictions on Oakey Blvd near MLK Blvd. Follow posted detours. Officer assistance.
Shadow Ln/Ellis Ave   TBD Night Lane restrictions on Shadow Ln, Charleston Blvd to Ellis Ave
Day Lane restrictions on Ellis Ave, Shadow Ln to Desert Ln

Night work hours are generally 7pm – 5am                                   Dates and times subject to change due to weather and field conditions.

 

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, AS OF DECEMBER 9:

 

    Location Date Time of Day Details
Major Spaghetti Bowl Ramp Closures / Detours – Use Alternate Routes When Possible
I-15 to US 95 N Ramps
I-15 SB to US 95 NB Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 South to US 95 North CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound then turn south on MLK Blvd for access to US 95 North.
I-15 NB to US 95 NB Ongoing –

Feb 2017

24/7 Ramp Rerouted: Ramp from I-15 North to US 95 North detoured onto the MLK Blvd exit ramp and back onto US 95 North via a temporary detour. Reduced speed, one lane.
NB MLK Off-Ramp
US 95 NB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from US 95 North to MLK Blvd CLOSED. Detour: Traffic will continue on US 95 North to Rancho Dr and turn around on US 95 South to exit at MLK Blvd.
I-15 NB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 North to MLK Blvd CLOSED. Detour: Traffic will exit Charleston Blvd westbound and turn north to access MLK Blvd.
I-15 SB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 South to MLK Blvd CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound to access MLK Blvd.
US 95: Rancho Dr to Spaghetti Bowl 12/5 – 12/22 Night Lane restrictions on US 95 in both directions between Rancho Dr and the Spaghetti Bowl
I-15 @ US 95   12/11 – 12/16 Night Right lane closure: I-15 northbound and southbound at US 95
US 95/Casino Center 12/12 – 12/14 Night Multiple lane closures: US 95 southbound from Spaghetti Bowl to Casino Center Blvd
MLK Blvd on-ramp

to US 95 NB

12/15 Night Ramp Closure: MLK Blvd on-ramp to US 95 northbound closed
US 95 SB/Rancho Dr Exit 12/16 Night Ramp Closure: US 95 southbound off-ramp to Rancho Dr closed
Grand Central Pkwy/ Charleston Blvd 12/12 – 12/16 Day or Night Lane restrictions on westbound Charleston Blvd at Grand Central Pkwy
Lane restrictions on northbound Grand Central Pkwy, Charleston Blvd to LV Premium Outlet Dr
US 95 NB near

Spaghetti Bowl

12/12 – 2/3 Night Left lane closure on US 95 (I-515) northbound near exit ramp to I-15 southbound
Alta Dr/MLK Blvd 12/12 – ongoing Night Lane restrictions an Alta Dr, both directions between I-15 and Shadow Ln
Lane restrictions on MLK Blvd at Alta Dr
Desert Ln Ongoing – 12/16 Day Lane restrictions on Desert Ln, Alta Dr to Hastings Ave
Charleston Blvd Ongoing – 12/16 Night Lane restrictions on Charleston Blvd, both directions between Shadow Ln and I-15
Shadow Ln/Ellis Ave Ongoing – 1/17 Night Lane restrictions on Shadow Ln, Charleston Blvd to Ellis Ave
Day Lane restrictions on Ellis Ave, Shadow Ln to Desert Ln
MLK Blvd/US 95 Ongoing – 2/23 Night Lane restrictions on MLK Blvd northbound at US 95

Upcoming Work

Location Date Time of Day Details
MLK Blvd at US 95 12/20 at 7pm –

12/21 at 6am

11 hrs Road Closure: MLK Blvd closed in both directions between Bonanza Rd and US 95 southbound
US 95 NB/Casino Ctr 12/19 – 1/12 Night Left lane closure on US 95 (I-515) northbound near Casino Center
MLK Blvd/Oakey Blvd TBD Day Lane restrictions on MLK Blvd near Oakey Blvd. Follow posted detours. Officer assistance.
Lane restrictions on Oakey Blvd near MLK Blvd. Follow posted detours. Officer assistance.

Night work hours are generally 7pm – 5am                                 Dates and times subject to change due to weather and field conditions.

 

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, AS OF DECEMBER 2:

Upcoming Work

Location Date Time of Day Details
US 95 SB/Rancho Dr Exit 12/16 Night Ramp Closure: US 95 southbound off-ramp to Rancho Dr closed
MLK Blvd at US 95 12/20 at 7pm –

12/21 at 6am

11 hrs Road Closure: MLK Blvd closed in both directions between Bonanza Rd and US 95 southbound
Grand Central Pkwy/ Charleston Blvd 12/12 – 12/16 Day or Night Lane restrictions on westbound Charleston Blvd at Grand Central Pkwy
Lane restrictions on northbound Grand Central Pkwy between Charleston Blvd and LV Premium Outlet Dr
US 95 NB near

Spaghetti Bowl

12/12 – 2/3 Night Left lane closure on US 95 (I-515) northbound near exit ramp to I-15 southbound
Alta Dr/MLK Blvd 12/12 – ongoing Night Lane restrictions an Alta Dr, both directions between I-15 and Shadow Ln
Lane restrictions on MLK Blvd at Alta Dr
US 95 NB/Casino Ctr 12/19 – 1/12 Night Left lane closure on US 95 (I-515) northbound near Casino Center
MLK Blvd/Oakey Blvd TBD Day Lane restrictions on MLK Blvd near Oakey Blvd. Follow posted detours. Officer assistance.
Lane restrictions on Oakey Blvd near MLK Blvd. Follow posted detours. Officer assistance.

Night work hours are generally 7pm – 5am                                 Dates and times subject to change due to weather and field conditions.

 

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, AS OF NOVEMBER 23:

    Location Date Time of Day Details
Major Spaghetti Bowl Ramp Closures / Detours – Use Alternate Routes When Possible
I-15 to US 95 N Ramps
I-15 SB to US 95 NB Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 South to US 95 North CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound then turn south on MLK Blvd for access to US 95 North.
I-15 NB to US 95 NB Ongoing –

Feb 2017

24/7 Ramp Rerouted: Ramp from I-15 North to US 95 North detoured onto the MLK Blvd exit ramp and back onto US 95 North via a temporary detour. Reduced speed, one lane.
NB MLK Off-Ramp
US 95 NB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from US 95 North to MLK Blvd CLOSED. Detour: Traffic will continue on US 95 North to Rancho Dr and turn around on US 95 South to exit at MLK Blvd.
I-15 NB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 North to MLK Blvd CLOSED. Detour: Traffic will exit Charleston Blvd westbound and turn north to access MLK Blvd.
I-15 SB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 South to MLK Blvd CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound to access MLK Blvd.
US 95: Rancho Dr to Spaghetti Bowl 11/28 – 12/22 Night Lane restrictions on US 95 in both directions between Rancho Dr and the Spaghetti Bowl
Symphony Park Ave 11/28 Night Lane restrictions on westbound Symphony Park Ave, Grand Central Pkwy to MLK Blvd
Alta Dr 11/28 – 12/6 Night Lane restrictions on Alta Dr, both directions between I-15 to Shadow Ln
Charleston Blvd 11/28 – 12/14 Night Lane restrictions on Charleston Blvd, both directions between Shadow Ln to I-15
Desert Ln Ongoing – 12/12 Day Lane restrictions on Desert Ln, Alta Dr to Hastings Ave
Bearden Dr Ongoing – 12/22 Day Lane restrictions on Bearden Dr. Flagger assistance.
Shadow Ln/Ellis Ave Ongoing – 1/17 Night Lane restrictions on Shadow Ln, Charleston Blvd to Ellis Ave
Day Lane restrictions on Ellis Ave, Shadow Ln to Desert Ln
MLK Blvd/US 95 Ongoing Night Lane restrictions on MLK Blvd northbound and southbound at US 95

Upcoming Work

Location Date Time of Day Details
US 95 SB/Rancho Dr Exit TBD Night Ramp Closure: US 95 southbound off-ramp to Rancho Dr closed
US 95 NB near

Spaghetti Bowl

12/5 – 1/12 Night Left lane closure on US 95 (I-515) northbound near exit ramp to I-15 southbound
US 95 NB/Casino Ctr 12/8 – 1/12 Night Left lane closure on US 95 (I-515) northbound near Casino Center
Alta Dr/MLK Blvd 12/20 – 1/9 Night Lane restrictions an Alta Dr, both directions between I-15 to Shadow Ln
Lane restrictions on MLK Blvd at Alta Dr
MLK Blvd/Oakey Blvd TBD Day Lane restrictions on MLK Blvd near Oakey Blvd. Follow posted detours. Officer assistance.
Lane restrictions on Oakey Blvd near MLK Blvd. Follow posted detours. Officer assistance.

Night work hours are generally 7pm – 5am                                  Dates and times subject to change due to weather and field conditions.

 

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, AS OF NOVEMBER 18:

    Location Date Time of Day Details
Major Spaghetti Bowl Ramp Closures / Detours – Use Alternate Routes When Possible
I-15 to US 95 N Ramps
I-15 SB to US 95 NB Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 South to US 95 North CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound then turn south on MLK Blvd for access to US 95 North.
I-15 NB to US 95 NB Ongoing –

Feb 2017

24/7 Ramp Rerouted: Ramp from I-15 North to US 95 North detoured onto the MLK Blvd exit ramp and back onto US 95 North via a temporary detour. Reduced speed, one lane.
NB MLK Off-Ramp
US 95 NB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from US 95 North to MLK Blvd CLOSED. Detour: Traffic will continue on US 95 North to Rancho Dr and turn around on US 95 South to exit at MLK Blvd.
I-15 NB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 North to MLK Blvd CLOSED. Detour: Traffic will exit Charleston Blvd westbound and turn north to access MLK Blvd.
I-15 SB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 South to MLK Blvd CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound to access MLK Blvd.
US 95: Rancho Dr to Spaghetti Bowl 11/18 Night Lane restrictions on US 95 in both directions between Rancho Dr and the Spaghetti Bowl
Charleston Blvd 11/20 – 11/22 Night Lane restrictions on Charleston Blvd, both directions from Shadow Ln to I-15
Alta/MLK Blvd 11/20 – 11/22 Night Lane restrictions on Alta Dr, both directions from I-15 to Shadow Ln
Lane restrictions on MLK Blvd at Alta Dr
Bearden Dr 11/21 – 12/22 Day Lane restrictions on Bearden Dr. Flagger assistance.
Wyoming Ave/

Industrial Rd

11/21 Night Lane restrictions on Wyoming Ave, Western Ave to Industrial Rd
Lane restrictions on Industrial Rd, Wyoming Ave to New York Ave
Shadow Ln/Ellis Ave 11/22 – 1/11 Night Lane restrictions on Shadow Ln, Charleston Blvd to Ellis Ave
Day Lane restrictions on Ellis Ave, Shadow Ln to Desert Ln
Desert Ln Ongoing – 12/16 Day Lane restrictions on Desert Ln, Alta Dr to Hastings Ave
MLK Blvd/US 95 Ongoing Night Lane restrictions on MLK Blvd northbound and southbound at US 95
Intermittent lane restrictions on MLK Blvd on-ramp to US 95 northbound

Upcoming Work

Location Date Time of Day Details
US 95: Rancho Dr to Spaghetti Bowl 11/27 – 12/20 Night Lane restrictions on US 95 in both directions between Rancho Dr and the Spaghetti Bowl
US 95 SB/Rancho Dr Exit TBD Night Ramp Closure: US 95 southbound off-ramp to Rancho Dr closed
US 95 NB near

Spaghetti Bowl

12/5 – 1/12 Night Left lane closure on US 95 (I-515) northbound near exit ramp to I-15 southbound
US 95 NB/Casino Ctr 12/8 – 1/12 Night Left lane closure on US 95 (I-515) northbound near Casino Center
Alta/MLK Blvd 12/20 – 1/9 Night Lane restrictions an Alta Dr, both directions from I-15 to Shadow Ln
Lane restrictions on MLK Blvd at Alta Dr
MLK Blvd/Oakey Blvd TBD Day Lane restrictions on MLK Blvd near Oakey Blvd. Follow posted detours. Officer assistance.
Lane restrictions on Oakey Blvd near MLK Blvd. Follow posted detours. Officer assistance.

Night work hours are generally 9pm – 6am                                    Dates and times subject to change due to weather and field conditions.

 

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, AS OF NOVEMBER 11:

    Location Date Time of Day Details
Major Spaghetti Bowl Ramp Closures / Detours – Use Alternate Routes When Possible
I-15 to US 95 N Ramps
I-15 SB to US 95 NB Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 South to US 95 North CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound then turn south on MLK Blvd for access to US 95 North.
I-15 NB to US 95 NB Ongoing –

Feb 2017

24/7 Ramp Rerouted: Ramp from I-15 North to US 95 North detoured onto the MLK Blvd exit ramp and back onto US 95 North via a temporary detour. Reduced speed, one lane.
NB MLK Off-Ramp
US 95 NB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from US 95 North to MLK Blvd CLOSED. Detour: Traffic will continue on US 95 North to Rancho Dr and turn around on US 95 South to exit at MLK Blvd.
I-15 NB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 North to MLK Blvd CLOSED. Detour: Traffic will exit Charleston Blvd westbound and turn north to access MLK Blvd.
I-15 SB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 South to MLK Blvd CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound to access MLK Blvd.
US 95 SB @ I-15 11/13 Night Left shoulder closure on ramp from US 95 SB to I-15 NB
Right shoulder closure on US 95 SB at I-15
Alta Dr 11/13 – 11/18 Night Lane restrictions on westbound Alta Dr, MLK Blvd to Shadow Ln
Charleston Blvd 11/13 – 11/23 Night Lane restrictions on eastbound and westbound Charleston Blvd, Shadow Ln to I-15
US 95: Rancho to Spaghetti Bowl 11/14 – 12/5 Night Lane restrictions on US 95 in both directions between Rancho Dr and the Spaghetti Bowl
Grand Central Pkwy 11/14 Night Lane restrictions on northbound Grand Central Pkwy at Iron Horse Ct
Desert Ln Ongoing – 12/16 Day Lane restrictions on Desert Ln, Alta Dr to Hastings Ave
Permanent 24/7 Street Closure: Desert Ln between Ellis Ave and Charleston Blvd permanently closed
Western Ave Permanent 24/7 Street parking prohibited on Western Ave between Oakey/Wyoming and Wall St
MLK Blvd/US 95 Ongoing Night Lane restrictions on MLK Blvd northbound and southbound at US 95
Intermittent lane restrictions on MLK Blvd on-ramp to US 95 northbound
MLK Blvd/Oakey Blvd Ongoing  – 11/28 Day Lane restrictions on MLK Blvd near Oakey Blvd. Follow posted detours. Officer assistance.
Day Lane restrictions on Oakey Blvd near MLK Blvd. Follow posted detours. Officer assistance.

Upcoming Work

Location Date Time of Day Details
US 95 SB/Rancho Dr Exit TBD Night Ramp Closure: US 95 southbound off-ramp to Rancho Dr closed
Shadow Ln 11/22 – 1/11 TBD Lane restrictions on Shadow Ln, Charleston Blvd to Ellis Ave
US 95 NB near

Spaghetti Bowl

11/27 – 1/4 Night Left lane closure on US 95 (I-515) northbound near exit ramp to I-15 southbound
US 95 NB/Casino Ctr 11/30 – 1/4 Night Left lane closure on US 95 (I-515) northbound near Casino Center

Night work hours are generally 9pm – 6am                                   Dates and times subject to change due to weather and field conditions.

 

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, AS OF NOVEMBER 4:

    Location Date Time of Day Details
Major Spaghetti Bowl Ramp Closures / Detours – Use Alternate Routes When Possible
I-15 to US 95 N Ramps
I-15 SB to US 95 NB Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 South to US 95 North CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound then turn south on MLK Blvd for access to US 95 North.
I-15 NB to US 95 NB Ongoing –

Feb 2017

24/7 Ramp Rerouted: Ramp from I-15 North to US 95 North detoured onto the MLK Blvd exit ramp and back onto US 95 North via a temporary detour. Reduced speed, one lane.
NB MLK Off-Ramp
US 95 NB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from US 95 North to MLK Blvd CLOSED. Detour: Traffic will continue on US 95 North to Rancho Dr and turn around on US 95 South to exit at MLK Blvd.
I-15 NB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 North to MLK Blvd CLOSED. Detour: Traffic will exit Charleston Blvd westbound and turn north to access MLK Blvd.
I-15 SB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 South to MLK Blvd CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound to access MLK Blvd.
Industrial Rd 11/6 Night Lane restrictions on Industrial Rd, New York Ave to Wyoming Ave
Wyoming Ave 11/6 Night Lane restrictions on eastbound Wyoming Ave, UP Railroad to Industrial Rd
Shadow Ln 11/6 – 11/15 Day/ Night Lane restrictions on Shadow Ln, Charleston Blvd to Ellis Ave
Desert Ln 11/7 – 11/10 Day Lane restrictions on Desert Ln, Alta Dr to Hastings Ave
11/8 – Permanent 24/7 Street Closure: Desert Ln between Ellis Ave and Charleston Blvd permanently closed
Western Ave 11/10 – Ongoing 24/7 Lane restrictions on Western Ave, Wyoming/Oakey to Charleston Blvd
Street parking permanently prohibited on Western Ave between Oakey/Wyoming and Wall St
MLK Blvd/US 95 Ongoing Night Lane restrictions on MLK Blvd northbound and southbound at US 95
Iron Horse Ct Ongoing – 11/15 Night Lane restrictions on Iron Horse Ct in both directions
Grand Central Pkwy Ongoing – 11/15 Night Lane restrictions on Grand Central Pkwy, Bonneville Ave to Charleston Blvd
11/8 Night Major lane restrictions on Grand Central Pkwy, Bonneville Ave to Charleston Blvd.

Officer assistance.

Charleston Blvd Ongoing – 11/15 Night Lane restrictions on eastbound Charleston Blvd, Shadow Ln to Commerce St
Lane restrictions on westbound Charleston Blvd, Commerce St to Shadow Ln
11/9 Night Major lane restrictions on Charleston Blvd, Commerce St to I-15. Officer assistance.
MLK Blvd/Oakey Blvd Ongoing  – 11/28 Day Lane restrictions on MLK Blvd near Oakey Blvd. Follow posted detours. Officer assistance.
Day Lane restrictions on Oakey Blvd near MLK Blvd

Upcoming Work

Location Date Time of Day Details
US 95 SB/Rancho Dr Exit TBD Night Ramp Closure: US 95 southbound off-ramp to Rancho Dr closed
US 95 NB near

Spaghetti Bowl

11/13 – 2/22 Night Left lane closure on US 95 (I-515) northbound near exit ramp to I-15 southbound
US 95 NB/Casino Ctr 11/16 – 12/22 Night Left lane closure on US 95 (I-515) northbound near Casino Center

Night work hours are generally 9pm – 6am                                Dates and times subject to change due to weather and field conditions.

 

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, AS OF OCTOBER 28:

    Location Date Time of Day Details
MLK Blvd at US 95 10/28 at 10pm – 10/31 at 5am 24/7 Street Closure: MLK Blvd closed in both directions at US 95, between US 95 and Bonanza Rd for bridge demolition. Follow posted detours. Sidewalks also closed, no pedestrian access.
MLK Blvd On-Ramp to US 95 NB 10/28 at 10pm – 10/31 at 5am 24/7 Ramp Closure: MLK Blvd on-ramp to US 95 NB closed for bridge demolition
Major Spaghetti Bowl Ramp Closures / Detours – Use Alternate Routes When Possible
I-15 to US 95 N Ramps
I-15 SB to US 95 NB Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 South to US 95 North CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound then turn south on MLK Blvd for access to US 95 North.
I-15 NB to US 95 NB Ongoing –

Feb 2017

24/7 Ramp Rerouted: Ramp from I-15 North to US 95 North detoured onto the MLK Blvd exit ramp and back onto US 95 North via a temporary detour. Reduced speed, one lane.
NB MLK Off-Ramp
US 95 NB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from US 95 North to MLK Blvd CLOSED. Detour: Traffic will continue on US 95 North to Rancho Dr and turn around on US 95 South to exit at MLK Blvd.
I-15 NB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 North to MLK Blvd CLOSED. Detour: Traffic will exit Charleston Blvd westbound and turn north to access MLK Blvd.
I-15 SB to MLK Blvd Ongoing –

Feb 2017

24/7 Ramp Closure: Ramp from I-15 South to MLK Blvd CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound to access MLK Blvd.
Desert Ln 10/28 – 11/4 Day Lane restrictions on Desert Ln, Alta Dr and Hastings Ave
I-15 NB south of US 95 10/30 – 11/2 Night Right lane and shoulder restrictions on NB I-15 south of Spaghetti Bowl
I-15 SB south of US 95 10/30,

11/1 – 11/ 2

Night Right lane and shoulder restrictions on SB I-15 south of Spaghetti Bowl
Shadow Ln 10/31 Night Lane restrictions on Shadow Ln south of Charleston
Industrial Rd 11/2 – 11/3 Night Lane restrictions on Industrial Rd, New York Ave to Wyoming Ave
Wyoming Ave 11/3 Night Lane restrictions on eastbound Wyoming Ave, UP Railroad to Industrial Rd
MLK Blvd/US 95 Ongoing Night Lane restrictions on MLK Blvd northbound and southbound at US 95
Symphony Park Ave Ongoing – 10/28 24/7 Lane restrictions on Symphony Park Ave, Grand Central Pkwy to MLK Blvd
Iron Horse Ct Ongoing – 11/15 Night Lane restrictions on Iron Horse Ct in both directions
Grand Central Pkwy Ongoing – 11/15 Night Lane restrictions on Grand Central Pkwy, Bonneville Ave to Charleston Blvd
Charleston Blvd Ongoing – 11/15 Night Lane restrictions on eastbound Charleston Blvd, Shadow Ln to Commerce St
Lane restrictions on westbound Charleston Blvd, Commerce St to Shadow Ln
MLK Blvd/Oakey Blvd Ongoing  – 11/28 Day Lane restrictions on MLK Blvd near Oakey Blvd. Follow posted detours. Officer assistance.
Day Lane restrictions on Oakey Blvd near MLK Blvd

Upcoming Work

 

Location Date Time of Day Details
US 95 SB/

Rancho Dr Exit

TBD

(11/6 or 11/7)

Night Ramp Closure: US 95 southbound off-ramp to Rancho Dr closed
Charleston/

Grand Central Pkwy

11/6 – 11/8 Night Major lane restrictions on Charleston Blvd, I-15 to Grand Central Pkwy
Major lane restrictions on Grand Central Pkwy, Bonneville Ave to Charleston Blvd
Western Ave 11/10 – Ongoing 24/7 Lane restrictions on Western Ave near Wall St
Street parking permanently prohibited on Western Ave between Oakey/Wyoming and Wall Street
US 95 NB near Spaghetti Bowl 11/14 – 12/21 Night Left lane closure on US 95 (I-515) northbound near exit ramp to I-15 southbound
US 95 NB/Casino Ctr 11/15 – 1/17 Night Left lane closure on US 95 (I-515) northbound near Casino Center

Night work hours are generally 9pm – 6am                             Dates and times subject to change due to weather and field conditions.

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, AS OF OCTOBER 21:

    Location Date Time of Day Details
MLK Blvd On-Ramp

to US 95 NB

Opens 10/25! 24/7 Ramp Closure: MLK Blvd on-ramp to US 95 North closed
Car-Nado: Major Spaghetti Bowl Ramp Closures / Detours – Use Alternate Routes When Possible
I-15 to US 95 N Ramps
I-15 SB to US 95 NB 10/26 at 10pm – Feb 2017 24/7 Ramp Closure: Ramp from I-15 South to US 95 North CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound then turn south on MLK Blvd for access to US 95 North.
I-15 NB to US 95 NB 10/28 at 5am – Feb 2017 24/7 Ramp Rerouted: Ramp from I-15 North to US 95 North detoured onto the MLK Blvd exit ramp and back onto US 95 North via a temporary detour. Reduced speed, one lane.
NB MLK Off-Ramp
US 95 NB to MLK Blvd 10/26 at 10pm – Feb 2017 24/7 Ramp Closure: Ramp from US 95 North to MLK Blvd CLOSED. Detour: Traffic will continue on US 95 North to Rancho Dr and turn around on US 95 South to exit at MLK Blvd.
I-15 NB to MLK Blvd 10/26 at 10pm– Feb 2017 24/7 Ramp Closure: Ramp from I-15 North to MLK Blvd CLOSED. Detour: Traffic will exit Charleston Blvd westbound and turn north to access MLK Blvd.
I-15 SB to MLK Blvd 10/26 at 10pm – Feb 2017 24/7 Ramp Closure: Ramp from I-15 South to MLK Blvd CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound to access MLK Blvd.
MLK Blvd at US 95 10/28 at 10pm – 10/31 at 5am 24/7 Street Closure: MLK Blvd closed in both directions at US 95, between Mineral Ave and Bonanza Rd. Follow posted detours.
US 95 SB/Rancho Dr Exit 10/24 Night Ramp Closure: US 95 southbound off-ramp to Rancho Dr closed
Industrial Rd 10/23 – 10/24 Night Lane restrictions on Industrial Rd, New York Ave to Wyoming Ave
MLK Blvd/US 95 Ongoing – 10/25 24/7 Intermittent closure of right lane on southbound MLK Blvd near US 95 overpass
Intermittent closure of sidewalk on west side of MLK Blvd between Bonanza Rd

and Mesquite Ave at the US 95 overpass

Ongoing Night Lane restrictions on MLK Blvd northbound and southbound at US 95
Ongoing – 10/28 Night Lane restrictions on northbound MLK Blvd off-ramp from I-15/US 95
Symphony Park Ave Ongoing – 10/28 24/7 Lane restrictions on Symphony Park Ave, Grand Central Pkwy to MLK Blvd
Iron Horse Ct Ongoing – 11/15 Night Lane restrictions on Iron Horse Ct in both directions
MLK Blvd/Oakey Blvd Ongoing  – 11/28 Day Lane restrictions on MLK Blvd near Oakey Blvd. Follow posted detours. Officer assistance.
Day Lane restrictions on Oakey Blvd near MLK Blvd
Charleston Blvd Ongoing – 11/15 Night Lane restrictions on eastbound Charleston Blvd, Shadow Ln to Commerce St
Lane restrictions on westbound Charleston Blvd, Commerce St to Shadow Ln
Grand Central Pkwy Ongoing – 11/15 Night Lane restrictions on Grand Central Pkwy between Bonneville Ave and Charleston Blvd

Upcoming Work

Location Date Time of Day Details
Western Ave 11/3 – Ongoing 24/7 Lane restrictions on Western Ave near Wall St
Street parking will be permanently prohibited on both sides of Western Ave between Oakey/Wyoming and Wall Street
Charleston/

Grand Central Pkwy

11/6 – 11/8 Night Major lane restrictions on Charleston Blvd between I-15 and Grand Central Pkwy

Major lane restrictions on Grand Central Pkwy between Bonneville and Charleston

US 95 NB near Spaghetti Bowl 11/14 – 12/21 Night Left lane closure on US 95 (I-515) northbound near exit ramp to I-15 southbound
US 95 NB/Casino Ctr 11/15 – 1/17 Night Left lane closure on US 95 (I-515) northbound near Casino Center

Night work hours are generally 9pm – 6am                           Dates and times subject to change due to weather and field conditions.

 

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, AS OF OCTOBER 14:

    Location Date Time of Day Details
Grand Central Pkwy/

I-15 NB Ramps/

LV Premium Outlet Dr

10/14 at 8pm – 10/17 at 5am 24/7 Motorists exiting I-15 northbound to Charleston westbound (Exit 41B) will not be able to access Grand Central Pkwy. Detour: Traffic will be diverted to Charleston Blvd westbound and detoured around to Grand Central Pkwy.
Northbound Grand Central Pkwy to I-15 North detoured onto Iron Horse Ct
10/14 at 8pm – 10/15 at 12pm 16 hrs Ramp Closure: Grand Central Pkwy and Iron Horse Ct access to I-15 North on-ramp closed.

Expect detours.

MLK Blvd On-Ramp

to US 95 NB

Ongoing – 10/25 24/7 Ramp Closure: MLK Blvd on-ramp to US 95 North closed
US 95 SB/Rancho Dr Exit 10/19 Night Ramp Closure: US 95 southbound off-ramp to Rancho Dr closed
I-15 NB/Charleston WB 10/7 – 10/17 Night Lane restrictions on I-15 North exit to Charleston Blvd westbound and Grand Central Pkwy
Iron Horse Ct 10/9 – 10/14 Night Lane restrictions on Iron Horse Ct in both directions
MLK Blvd/Oakey Blvd 10/18 – 11/21 Day Lane restrictions on MLK Blvd near Oakey Blvd. Follow posted detours. Officer assistance.
Day Lane restrictions on Oakey Blvd near MLK Blvd.
US 95 NB/MLK Blvd 10/20 Night US 95 northbound off-ramp to MLK Blvd closed
Industrial Rd 10/23 – 10/24 Night Lane restrictions on Industrial Rd, New York Ave to Wyoming Ave
Symphony Park Ave Ongoing – 10/28 24/7 Lane restrictions on Symphony Park Ave, Grand Central Pkwy to MLK Blvd
Charleston Blvd Ongoing – 11/15 Night Lane restrictions on eastbound Charleston Blvd, Shadow Ln to Commerce St
Lane restrictions on westbound Charleston Blvd, Commerce St to Shadow Ln
Grand Central Pkwy Ongoing – 11/15 Night Lane restrictions on Grand Central Pkwy between Bonneville Ave and Charleston Blvd
MLK Blvd/US 95 Ongoing 24/7 Intermittent closure of right lane on southbound MLK Blvd near US 95 overpass
Intermittent closure of sidewalk on west side of MLK Blvd between Bonanza Rd

and Mesquite Ave at the US 95 overpass

Ongoing Night Lane restrictions on MLK Blvd northbound and southbound at US 95
Lane restrictions on northbound MLK Blvd off-ramp from I-15/US 95

Upcoming Work

Location Date Time of Day Details
Major Spaghetti Bowl Ramp Closures / Detours – Use Alternate Routes When Possible
I-15 to US 95 N Ramps
I-15 SB to US 95 NB 10/26 – Feb 2017 24/7 Ramp Closure: Ramp from I-15 South to US 95 North CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound then turn south on MLK Blvd for access to US 95 North.
I-15 NB to US 95 NB 10/28 – Feb 2017 24/7 Ramp Rerouted: Ramp from I-15 North to US 95 North retoured onto the MLK Blvd exit ramp and back onto US 95 North via a temporary detour. Reduced speed, one lane.
NB MLK Off-Ramp
US 95 NB to MLK Blvd 10/26 – Feb 2017 24/7 Ramp Closure: Ramp from US 95 North to MLK Blvd CLOSED. Detour: Traffic will continue on US 95 North to Rancho Dr and turn around on US 95 South to exit at MLK Blvd.
I-15 NB to MLK Blvd 10/26 – Feb 2017 24/7 Ramp Closure: Ramp from I-15 North to MLK Blvd CLOSED. Detour: Traffic will exit Charleston Blvd westbound and turn north to access MLK Blvd.
I-15 SB to MLK Blvd 10/26 – Feb 2017 24/7 Ramp Closure: Ramp from I-15 South to MLK Blvd CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound to access MLK Blvd.
MLK Blvd at US 95 10/28 at 10pm – 10/31 at 5am* 24/7 Street Closure: MLK Blvd closed in both directions at US 95, between Mineral Ave and Bonanza Rd. Follow posted detours.
Western Ave TBD 24/7 Lane restrictions on Western Ave near Wall St
Desert Ln/Ellis Ave TBD Day Lane restrictions on Desert Ln, Ellis Ave to Charleston Blvd
Rancho Dr TBD Night Intermittent closure of right lane on southbound Rancho Dr near US 95 overpass
Intermittent sidewalk closures on west side of Rancho Dr between Mesquite Ave and Bonanza Rd at the US 95 overpass

Night work hours are generally 9pm – 6am

*Subject to change

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, WEEK OF OCTOBER 9:

Grand Central Pkwy/

I-15 NB Ramps/

LV Premium Outlet Dr

10/14 at 8pm – 10/17 at 5am 24/7 Motorists exiting I-15 northbound to Charleston westbound (Exit 41B) will not be able to access Grand Central Pkwy. Detour: Traffic will be diverted to Charleston Blvd westbound and detoured around to Grand Central Pkwy.
10/15 at 12 pm- 10/17 at 5 am Northbound Grand Central Pkwy to I-15 North detoured onto Iron Horse Ct
10/14 at 8pm – 10/15 at 12pm 16 hrs Ramp Closure: Grand Central Pkwy and Iron Horse Ct access to I-15 North on-ramp closed.

Expect detours.

MLK Blvd On-Ramp

to US 95 NB

Ongoing – 10/25 24/7 Ramp Closure: MLK Blvd on-ramp to US 95 North closed
Desert Ln/Hastings Ave Permanent 24/7 Desert Ln permanently closed between Charleston Blvd and Hastings Ave
Hastings Ave permanently closed between MLK Blvd and Desert Ln
I-15 NB/Charleston WB 10/7 – 10/17 Night Lane restrictions on I-15 North exit to Charleston Blvd westbound and Grand Central Pkwy
Iron Horse Ct 10/9 – 10/14 Night Lane restrictions on Iron Horse Ct in both directions
Oakey/MLK Blvd 10/11 Day Temporary closure of intersection at Oakey Blvd and MLK Blvd. Officer assistance.
Charleston Blvd Ongoing – 11/15 Night Lane restrictions on eastbound Charleston Blvd, Shadow Ln to Commerce St
Lane restrictions on westbound Charleston Blvd, Commerce St to Shadow Ln
Grand Central Pkwy Ongoing – 11/15 Night Lane restrictions on northbound and southbound Grand Central Pkwy, Bonneville Ave to Charleston Blvd
Symphony Park Ave Ongoing – 10/28 Day/ Night Lane restrictions on Symphony Park Ave, Grand Central Pkwy to MLK Blvd
MLK Blvd/US 95 Ongoing 24/7 Intermittent closure of right lane on southbound MLK Blvd near US 95 overpass
Intermittent closure of sidewalk on west side of MLK Blvd between Bonanza Rd

and Mesquite Ave at the US 95 overpass

Ongoing Night Lane restrictions on MLK Blvd northbound and southbound at US 95
Lane restrictions on northbound MLK Blvd off-ramp from I-15/US 95

Upcoming Work

Location Date Time of Day Details
Major Spaghetti Bowl Ramp Closures / Detours – Use Alternate Routes When Possible
I-15 to US 95 N Ramps
I-15 SB to US 95 NB 10/26 – Feb 2017 24/7 Ramp Closure: Ramp from I-15 South to US 95 North CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound then turn south on MLK Blvd for access to US 95 North.
I-15 NB to US 95 NB 10/28 – Feb 2017 24/7 Ramp Closure: Ramp from I-15 North to US 95 North detoured onto the MLK Blvd exit ramp and back onto US 95 North via a temporary detour. Reduced speed, one lane.
NB MLK Off-Ramp
US 95 NB to MLK Blvd 10/26 – Feb 2017 24/7 Ramp Closure: Ramp from US 95 North to MLK Blvd CLOSED. Detour: Traffic will continue on US 95 North to Rancho Dr and turn around on US 95 South to exit at MLK Blvd.
I-15 NB to MLK Blvd 10/28 – Feb 2017 24/7 Ramp Closure: Ramp from I-15 North to MLK Blvd CLOSED. Detour: Traffic will exit Charleston Blvd westbound and turn north to access MLK Blvd.
I-15 SB to MLK Blvd 10/28 – Feb 2017 24/7 Ramp Closure: Ramp from I-15 South to MLK Blvd CLOSED. Detour: Traffic will exit at Lake Mead Blvd westbound to access MLK Blvd.
MLK Blvd at US 95 10/28 – 10/30 24/7 MLK Blvd CLOSED in both directions at US 95 (Friday night – Sunday night). Follow posted detours.
Industrial/Wyoming 10/16 – 10/17 Night Lane restrictions on Industrial Rd, New York Ave to Wyoming Ave
10/16 – 10/17 Night Lane restrictions on Wyoming Ave, Industrial Rd to Western Ave
MLK Blvd/Oakey Blvd 10/17 – 11/8 Day Lane restrictions on MLK Blvd near Oakey Blvd. Follow posted detours. Officer assistance.
Day Lane restrictions on Oakey Blvd near MLK Blvd.
US 95 NB/MLK Blvd 10/19 Night Right lane closure on US 95 North near MLK Blvd
US 95 SB/

Rancho Dr Exit

TBD Night Intermittent night closures of the US 95 southbound off-ramp to Rancho Dr
Rancho Dr TBD Night Intermittent closure of right lane on southbound Rancho Dr near US 95 overpass
Intermittent sidewalk closures on west side of Rancho Dr between Mesquite Ave and Bonanza Rd at the US 95 overpass

Night work hours are generally 9pm – 6am

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, WEEK OF OCTOBER 2:

Location Date Time of Day Details
Desert Ln/Hastings Ave 10/3 24/7 Desert Ln permanently closed between Charleston Blvd and Hastings Ave.

Hastings Ave permanently closed between MLK Blvd and Desert Ln.

I-15 NB to US 95 NB 10/5 Night Intermittent closure of the ramp from I-15 northbound to US 95 northbound

between 1am and 5am

I-15 SB & US 95 NB to MLK Blvd     10/7 Night Exit to MLK Blvd from I-15 southbound and US 95 northbound closed.

Detoured to Rancho Drive exit.

MLK Blvd On-Ramp

to US 95 NB

Ongoing – 11/15 24/7 Ramp Closure: MLK Blvd on-ramp to US 95 northbound closed
Charleston Blvd 9/25 – 10/7 Night Lane restrictions on eastbound Charleston Blvd, Shadow Ln to Commerce St
Lane restrictions on westbound Charleston Blvd, Commerce St to Shadow Ln
Symphony Park Ave 9/25 – Ongoing Night Lane restrictions on Symphony Park Ave, Grand Central Pkwy to MLK Blvd
Desert Ln 10/2 – 10/7 Night Lane restrictions on Desert Ln, Hastings Ave to Pinto Ln
Alta/Bonneville/MLK 10/3 -10/7 Night Lane restrictions on westbound Bonneville Ave, I-15 to MLK Blvd
Ongoing Night Lane restrictions on eastbound Alta Dr, Desert Ln to I-15
Night Lane restrictions on northbound MLK Blvd at Alta
Grand Central Pkwy Ongoing Night Lane restrictions on northbound and southbound Grand Central Pkwy, Bonneville Ave to Charleston Blvd
MLK Blvd/US 95 Ongoing 24/7 Intermittent closure of right lane on southbound MLK Blvd near US 95 overpass
Intermittent closure of sidewalk on west side of MLK Blvd between Bonanza Rd

and Mesquite Ave at the US 95 overpass

Ongoing Night Lane restrictions on MLK Blvd northbound and southbound at US 95
Lane restrictions on northbound MLK Blvd off-ramp from I-15/US 95

Upcoming Work

 

Location Date Time of Day Details
Grand Central Pkwy/

I-15 NB Ramps/

LV Premium Outlet Dr

10/14 at 8pm – 10/17 at 5am 24/7 Motorists exiting I-15 northbound to Charleston westbound (Exit 41B) will not be able to access Grand Central Pkwy. Traffic will be diverted to Charleston Blvd westbound and detoured around to Grand Central Pkwy.
Northbound Grand Central Pkwy to I-15 northbound detoured onto Iron Horse Ct
10/14 at 8pm – 10/15 at 12pm 16 hrs Grand Central Pkwy and Iron Horse Ct access to I-15 northbound on-ramp closed.

Expect detours.

Western Ave TBD 24/7 Lane restrictions on Western Ave near Wall St
Desert Ln/Ellis Ave TBD Day Lane restrictions on Desert Ln, Ellis Ave to Charleston Blvd
US 95 SB/

Rancho Dr Exit

TBD Night Intermittent night closures of the US 95 southbound off-ramp to Rancho Dr
Rancho Dr TBD Night Intermittent closure of right lane on southbound Rancho Dr near US 95 overpass
Intermittent sidewalk closures on west side of Rancho Dr between Mesquite Ave and Bonanza Rd at the US 95 overpass
MLK Blvd/Oakey Blvd TBD Day Lane restrictions on northbound and southbound MLK Blvd near Oakey Blvd
Day Lane restrictions on Oakey Blvd near MLK Blvd
Utah/Industrial TBD Night Lane restrictions on Utah Ave, Fairfield Ave to Industrial Rd
Industrial/Wyoming TBD Night Lane restrictions on Industrial Rd, New York Ave to Utah Ave
TBD Night Lane restrictions on Wyoming Ave, Western Ave to Fairfield Ave

Night work hours are generally 9pm – 6am

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, WEEK OF SEPTEMBER 25:

Location Date Time of Day Details
Symphony Park Ave 9/23 at 10pm – 9/26 at 5 am 24/7 Symphony Park Ave closed in both directions between Grand Central Pkwy and MLK Blvd
MLK Blvd On-Ramp to 

I-15 SB

9/23 Night MLK Blvd on-ramp to I-15 southbound closed
MLK Blvd On-Ramp

to US 95 NB

9/6 – 11/15 24/7 Ramp Closure: MLK Blvd on-ramp to US 95 northbound closed
US 95 SB to I-15 SB 9/23 Night Lane restrictions on ramp from US 95 southbound to I-15 southbound
US 95 over MLK Blvd 9/25 Night Shoulder closed on eastbound and westbound US 95 over MLK Blvd
Charleston Blvd 9/25 – 10/7 Night Lane restrictions on eastbound Charleston Blvd, Shadow Ln to Commerce St
Lane restrictions on westbound Charleston Blvd, Commerce St to Shadow Ln
Symphony Park Ave 9/25 – Ongoing Night Lane restrictions on Symphony Park Ave between Grand Central Pkwy and MLK Blvd
Alta Dr/MLK Blvd 9/25 – 9/29 Night Lane restrictions on Alta Dr, Desert Ln to I-15
Lane restrictions on northbound MLK Blvd at Alta Dr
Desert Ln 9/26 – 9/27 Night Lane restrictions on Desert Ln between Charleston Blvd and Pinto Ln
I-15 NB to US 95 NB 9/29 Night Intermittent closure of the ramp from I-15 northbound to US 95 northbound

between 1am and 5am

MLK Blvd/US 95 Ongoing 24/7 Intermittent closure of right lane on southbound MLK Blvd near US 95 overpass
Intermittent closure of sidewalk on west side of MLK Blvd between Bonanza Rd

and Mesquite Ave at the US 95 overpass

Ongoing Night Lane restrictions on MLK Blvd northbound and southbound at US 95
Lane restrictions on northbound MLK Blvd off-ramp from I-15/US 95
Grand Central Pkwy Ongoing Night Lane restrictions on northbound and southbound Grand Central Pkwy, Bonneville Ave to Charleston Blvd

Upcoming Work

 

Location Date Time of Day Details
Desert Ln 10/3 24/7 Street permanently closed between Charleston Blvd and Hastings Ave.
I-15 SB & US 95 NB to MLK Blvd     10/7 Night Exit to MLK Blvd from I-15 southbound and US 95 northbound closed.

Detoured to Rancho Drive exit off US 95 N.

Grand Central Pkwy/

I-15 NB Ramps/

LV Premium Outlet Dr

10/14 at 10pm – 10/17 at 5am Day/ Friday Night Motorists exiting I-15 northbound to Charleston westbound (Exit 41B) will not be able to access Grand Central Pkwy. Traffic will be diverted to Charleston Blvd westbound and detoured around to Grand Central Pkwy.
Southbound Grand Central Pkwy south of LV Premium Outlet Dr closed.
Northbound Grand Central Pkwy to I-15 northbound detoured onto Iron Horse Ct
10/15 – 10/16 Night Grand Central Pkwy and Iron Horse Ct access to I-15 northbound on-ramp closed.

Expect detours.

Utah/Industrial 10/2 Night Lane restrictions on Utah Ave between Fairfield Ave and Industrial Rd
Industrial/Wyoming 10/3 – 10/5 Night Lane restrictions on Industrial Ave between New York Ave and Utah Ave
10/5 Night Lane restrictions on Wyoming Ave between Western Ave and Fairfield Ave
Alta/Bonneville 10/6 Night Lane restrictions on westbound Bonneville Ave between I-15 and MLK Blvd
Western Ave TBD 24/7 Lane restrictions on Western Ave near Wall St
Desert Ln/Ellis Ave TBD Day Lane restrictions on Desert Ln, Ellis Ave to Charleston Blvd
US 95 SB/

Rancho Dr Exit

TBD Night Intermittent night closures of the US 95 southbound off-ramp to Rancho Dr
Rancho Dr TBD Night Intermittent closure of right lane on southbound Rancho Dr near US 95 overpass
Intermittent sidewalk closures on west side of Rancho Dr between Mesquite Ave and Bonanza Rd at the US 95 overpass
MLK Blvd/Oakey Blvd TBA Day Lane restrictions on MLK Blvd northbound and southbound near Oakey Blvd
Day Lane restrictions on Oakey near MLK Blvd

Night work hours are generally 9pm – 6am

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, WEEK OF SEPTEMBER 18:

Location Date Time of Day Details
Spaghetti Bowl Ramp

US 95 South

to

I-15 South

9/16 at 10pm –

9/18 at 10am

36 hrs Ramp Closure: Ramp from US 95 South to I-15 South closed
9/16 at 10pm –

9/18 at 10am

36 hrs Other Ramp Closures Associated with Spaghetti Bowl Ramp Closure:

– Ramp from MLK Blvd to I-15 South closed

– Ramp from Rancho Dr to I-15 South closed (Rancho on-ramp to 95 South open)

– Ramp from Washington/D Street to I-15 South closed

9/18 – Ongoing 24/7 Traffic Switch: Ramp from US 95 South to I-15 South in modified configuration, lanes shifted to left on existing ramp
MLK Blvd On-Ramp

to US 95 North

9/6 – 11/15 24/7 Ramp Closure: MLK Blvd on-ramp to US 95 northbound closed
MLK Blvd/US 95 9/6 – 11/15 24/7 Intermittent closure of right lane on southbound MLK Blvd near US 95 overpass
Intermittent closure of sidewalk on west side of MLK Blvd between Bonanza Rd and Mesquite Ave at the US 95 overpass
Ongoing Night Lane restrictions on MLK Blvd northbound and southbound at US 95
Lane restrictions on northbound MLK Blvd off-ramp from I-15/US 95
I-15/Charleston Ongoing 24/7 Traffic Switch: I-15 northbound off-ramp to Charleston Blvd westbound in temporary configuration. Reduced speeds on off-ramp.
Grand Central Pkwy Ongoing 24/7 Traffic Switch: Southbound lanes on Grand Central Pkwy, Iron Horse Ct to Charleston Blvd, shifted to the east.
Ongoing Night Lane restrictions on northbound and southbound Grand Central Pkwy, Bonneville Ave to Charleston Blvd
Charleston Blvd Ongoing Night Lane restrictions on eastbound Charleston Blvd, I-15 to Commerce St
Lane restrictions on westbound Charleston Blvd, Commerce St to MLK Blvd
  9/22 Night Lane restrictions on eastbound Charleston Blvd, Shadow Ln to Desert Ln
Symphony Park Ave 9/18-9/22 Night Lane restrictions on Symphony Park Ave,

Grand Central Pkwy to MLK Blvd

9/23 at 10pm –

9/25 at 5am

24/7 Street Closed: Symphony Park Ave closed in both directions between

Grand Central Pkwy and MLK Blvd

MLK Blvd/Oakey Blvd Ongoing Day Lane restrictions on northbound and southbound MLK Blvd near Oakey Blvd
Day Lane restrictions on Oakey Blvd near MLK Blvd
  Alta Dr   9/18 Night Lane restrictions on eastbound Alta Dr, Desert Ln to I-15
  Bonneville Ave   9/19 Night Lane restrictions on westbound Bonneville Ave, Grand Central Pkwy to MLK Blvd

Upcoming Work

Location Date Time of Day Details
Western Ave TBD 24/7 Lane restrictions on Western Ave near Wall St
Desert Ln/Ellis Ave TBD Day Lane restrictions on Desert Ln, Ellis Ave to Charleston Blvd
US 95 SB/

Rancho Dr Exit

TBD Night Intermittent night closures of the US 95 southbound off-ramp to Rancho Dr
Rancho Dr TBD Night Intermittent closure of right lane on southbound Rancho Dr near US 95 overpass
Intermittent sidewalk closures on west side of Rancho Dr between Mesquite Ave and Bonanza Rd at the US 95 overpass

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, WEEK OF SEPTEMBER 11:

Location Date Time of Day Details
Spaghetti Bowl Ramp

US 95 SB to I-15 SB

9/9 Night Left lane of ramp from US 95 southbound to I-15 southbound closed
9/16 at 10pm – 9/18 at 10am 36 hrs Ramp Closure: Ramp from US 95 southbound to I-15 southbound closed
9/18 – Ongoing 24/7 Traffic Switch: Ramp from US 95 southbound to I-15 southbound in modified configuration, lanes shifted to left on existing ramp
MLK Blvd On-Ramp

to US 95 NB

9/6 – 11/15 24/7 Ramp Closure: MLK Blvd on-ramp to US 95 northbound closed
MLK Blvd/US 95 9/6 – 11/15 24/7 Intermittent closure of right lane on southbound MLK Blvd near US 95 overpass
Intermittent closure of sidewalk on west side of MLK Blvd between Bonanza Rd and Mesquite Ave at the US 95 overpass
Ongoing Night Lane restrictions on MLK Blvd northbound and southbound at US 95
Lane restrictions on northbound MLK Blvd off-ramp from I-15/US 95
I-15/Charleston 9/10 – 9/11 Night Ramp Closure: Northbound I-15 exit to Charleston Blvd westbound closed
9/11 – Ongoing 24/7 Traffic Switch: I-15 northbound off-ramp to westbound Charleston Blvd in temporary configuration. Reduced speeds on off-ramp.
Grand Central Pkwy 9/10 Night Northbound Grand Central Pkwy closed from Charleston Blvd to LV Premium Outlet Dr
9/11 – Ongoing 24/7 Traffic Switch: Southbound lanes on Grand Central Pkwy, Iron Horse Ct to Charleston Blvd, shifted to the east.
Ongoing Night Lane restrictions on northbound and southbound Grand Central Pkwy, Bonneville Ave to Charleston Blvd
Charleston Blvd Ongoing Night Lane restrictions on eastbound Charleston Blvd, I-15 to Commerce St
Lane restrictions on westbound Charleston Blvd, Commerce St to MLK Blvd
Alta Dr/MLK Blvd 9/11 – 9/15 Night Lane restrictions on Alta Dr, MLK Blvd to I-15
Lane restrictions on northbound MLK Blvd at Alta Dr
I-15 SB at Spaghetti Bowl 9/12 – 9/14 Night Right lane of I-15 southbound closed near Spaghetti Bowl
Desert Ln 9/12 – 9/16 Day Lane restrictions on Desert Ln between Pinto Ln and Alta Dr.

Street parking on northbound Desert Ln will be restricted in this area.

MLK Blvd/Oakey Blvd 9/14 – Ongoing Day Lane restrictions on MLK Blvd northbound and southbound near Oakey Blvd
Day Lane restrictions on Oakey near MLK Blvd
Ellis Ave 9/15 – 9/16 Day Lane restrictions on Ellis Ave between Desert Ln and Shadow Ln

Upcoming Work

 

Location Date Time of Day Details
Alta Dr 9/18 Night Lane restrictions on eastbound Alta Dr, Desert Ln to I-15
Bonneville Ave 9/19 Night Lane restrictions on westbound Bonneville Ave, Grand Central Pkwy to MLK Blvd
Symphony Park Ave 9/23 at 10pm – 9/25 at 10am 24/7 Symphony Park Ave closed in both directions between Grand Central Pkwy and MLK Blvd
Western Ave TBD 24/7 Lane restrictions on Western Ave near Wall St
Desert Ln/Ellis Ave TBD Day Lane restrictions on Desert Ln, Ellis Ave to Charleston Blvd
US 95 SB/

Rancho Dr Exit

TBD Night Intermittent night closures of the US 95 southbound off-ramp to Rancho Dr
Rancho Dr TBD Night Intermittent closure of right lane on southbound Rancho Dr near US 95 overpass
Intermittent sidewalk closures on west side of Rancho Dr between Mesquite Ave and Bonanza Rd at the US 95 overpass

Night work hours are generally 9pm – 6am

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, WEEK OF SEPTEMBER 4:

Location Date Time of Day Details
MLK Blvd On-Ramp

to US 95 NB

9/6 – 11/15 24/7 Ramp Closure: MLK Blvd on-ramp to US 95 northbound closed
MLK Blvd/US 95 9/6 – 11/15 24/7 Intermittent closure of right lane on southbound MLK Blvd near US 95 overpass
Intermittent closure of sidewalk on west side of MLK Blvd between Bonanza Rd and Mesquite Ave at the US 95 overpass
Ongoing Night Lane restrictions on MLK Blvd northbound and southbound at US 95
Lane restrictions on northbound MLK Blvd off-ramp from I-15/US 95
Spaghetti Bowl Ramp Lane Reductions
I-15 NB to US 95 NB 9/6 Night Right lane of ramp from I-15 northbound to US 95 northbound closed
US 95 SB to I-15 SB 9/8 – 9/9 Night Left lane of ramp from US 95 southbound to I-15 southbound closed
US 95 SB/

Rancho Dr Exit

9/6 – 9/15 Night Intermittent night closures of the US 95 southbound off-ramp to Rancho Dr
October   Signal installation, new configuration with two right turn lanes
Rancho Dr 9/6 – 9/15 Night Intermittent closure of right lane on southbound Rancho Dr near US 95 overpass
Intermittent sidewalk closures on west side of Rancho Dr between Mesquite Ave and Bonanza Rd at the US 95 overpass
Oakey Blvd 9/6 Night Lane restrictions on eastbound Oakey Blvd from Kiltie Way to MLK Blvd
Alta Dr/MLK Blvd 9/6 – 9/8 Night Lane restrictions on Alta Dr, MLK Blvd to I-15
Night Lane restrictions on northbound MLK Blvd at Alta Dr
Bonneville Ave 9/8 Night Lane restrictions on westbound Bonneville Ave, Grand Central Pkwy to MLK Blvd
Desert Ln 9/8 – 9/9 Day Lane restrictions on Desert Ln between Pinto Ln and Alta Dr. Street parking on northbound Desert Ln will be restricted in this area.
I-15/Charleston 9/6 – 9/9 Night Lane restrictions on I-15 northbound off-ramp to Charleston westbound
9/10 Night Ramp Closure: Northbound I-15 exit to Charleston Blvd westbound closed
9/10 – Ongoing 24/7 Traffic Switch: I-15 northbound off-ramp to westbound Charleston Blvd in temporary configuration, west of current location. Reduced speeds on off-ramp.
Grand Central Pkwy 9/10 Night Northbound Grand Central Pkwy closed from Charleston Blvd to LV Premium Outlet Dr
9/11 – Ongoing 24/7 Traffic Switch: Southbound lanes on Grand Central Pkwy, Iron Horse Ct to Charleston Blvd, shifted to the east
Ongoing Night Lane restrictions on northbound and southbound Grand Central Pkwy, Bonneville Ave to Charleston Blvd
Charleston Blvd Ongoing Night Lane restrictions on eastbound Charleston Blvd, I-15 to Grand Central Pkwy
Lane restrictions on westbound Charleston Blvd, Grand Central Pkwy to MLK Blvd
Western Ave/Wall St Ongoing 24/7 Intersection of Wall St/Western Ave in temporary configuration.

Upcoming Work

Location Date Time of Day Details
Spaghetti Bowl

Ramp Closure

US 95 SB to I-15 SB

9/16 at 10pm – 9/18 at 10am 36 hrs Ramp Closure: Ramp from US 95 southbound to I-15 southbound closed
9/18 – Ongoing 24/7 Traffic Switch: Ramp from US 95 southbound to I-15 southbound in modified configuration, lanes shifted to left on existing ramp
MLK Blvd/Oakey Blvd 9/14 – Ongoing Day Lane restrictions on MLK Blvd northbound and southbound near Oakey Blvd
Oakey Blvd 9/14 – Ongoing Day Lane restrictions on Oakey near MLK Blvd
Ellis Ave 9/15 – 9/16 Day Lane restrictions on Ellis Ave between Desert Ln and Shadow Ln
Alta Dr 9/18 Night Lane restrictions on eastbound Alta Dr, Desert Ln to I-15
Bonneville Ave 9/19 Night Lane restrictions on westbound Bonneville Ave, Grand Central Pkwy to MLK Blvd
Symphony Park Ave 9/23 – 9/24 Night Symphony Park Ave closed in both directions Between Grand Central Pkwy and MLK Blvd
Western Ave TBD 24/7 Lane restrictions on Western Ave near Wall St
Desert Ln/Ellis TBD Day Lane restrictions on Desert Ln, Ellis Ave to Charleston Blvd

Night work hours are generally 9pm – 6am

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, WEEK OF AUGUST 28:

Location Date Time of Day Details
US 95 SB/

Rancho Dr Exit

8/7 9/2 24/7 Ramp Closure: US 95 southbound off-ramp to Rancho Dr closed
9/6 – 9/15 Night Intermittent night closures of this ramp
October Signal installation, new configuration with two right turn lanes
Rancho Dr 8/7 – 9/15 24/7 Intermittent closure of right lane on southbound Rancho Dr near US 95 overpass
Sidewalk closed on west side of Rancho Dr between Mesquite Ave and Bonanza Rd at the US 95 overpass
Alta Dr/MLK Blvd 8/28 – 9/1 Night Lane restrictions on Alta Dr, MLK Blvd to I-15
Night Lane restrictions on northbound MLK Blvd at Alta Dr
Symphony Park Ave 8/30 – 9/1 Night Lane restrictions on Symphony Park Ave, Grand Central Pkwy to MLK Blvd
Industrial Rd 9/1 – 9/2 Day Lane restrictions on Industrial Rd at Utah Ave
I-15/Charleston Blvd Ongoing Night Lane restrictions on I-15 northbound off-ramp to Charleston westbound
Charleston Blvd Ongoing Night Lane restrictions on eastbound Charleston Blvd, I-15 to Grand Central Pkwy
Lane restrictions on westbound Charleston Blvd, Grand Central Pkwy to MLK Blvd
8/28 – 8/29 Lane restrictions on Charleston Blvd between MLK Blvd and Shadow Ln
Grand Central Pkwy Ongoing Night Lane restrictions on southbound and/or northbound Grand Central Pkwy, LV Premium Outlet Dr to Charleston Blvd
Western Ave/Wall St Ongoing 24/7 Traffic Switch: Intersection of Wall St/Western Ave in temporary configuration.
MLK Blvd/US 95 Ongoing Night Lane restrictions on MLK Blvd on-ramp to US 95 northbound
Lane restrictions on northbound MLK Blvd off-ramp from I-15/US 95
Lane restrictions on northbound and southbound MLK Blvd near US 95

Upcoming Work

Location Date Time of Day Details
MLK Blvd On-Ramp

to US 95 NB

9/6 – 11/15 24/7 Ramp Closure: MLK Blvd on-ramp to US 95 northbound closed
 
US 95 SB to

I-15 SB Ramp

9/7 – 9/8 Night Left lane of US 95 southbound ramp to I-15 southbound closed
9/16 – 9/18 24/7 Ramp Closure: Ramp from US 95 southbound to I-15 southbound closed
9/18 – Ongoing 24/7 Traffic Switch: Ramp from US 95 southbound to I-15 southbound in modified configuration, lanes shifted to left on existing ramp
Oakey Blvd 9/5 Night Lane restrictions on eastbound Oakey Blvd from Kiltie Way to MLK Blvd
I-15/Charleston 9/7 – Ongoing 24/7 Traffic Switch: I-15 northbound off-ramp to westbound Charleston Blvd in temporary configuration, west of current location. Reduced speeds on off-ramp.
Alta Dr 9/6 – 9-7 Night Lane restrictions on eastbound Alta Dr, Desert Ln to MLK Blvd
Bonneville Ave 9/8 Night Lane restrictions on westbound Bonneville Ave, Grand Central Pkwy to MLK Blvd
Desert Ln 9/8 – 9/9 Day Lane restrictions on Desert Ln between Pinto Ln and Alta Dr. Street parking on northbound Desert Ln will be restricted in this area.
Grand Central Pkwy 9/7 – Ongoing 24/7 Traffic Switch: Southbound lanes on Grand Central Pkwy, Iron Horse Ct to Charleston Blvd, shifted to the east
Ellis Ave 9/14 – 9/15 Day Lane restrictions on Ellis Ave between Desert Ln and Shadow Ln
Desert Ln/Ellis TBD Day Lane restrictions on Desert Ln, Ellis Ave to Charleston Blvd

Night work hours are generally 9pm – 6am

 

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, WEEK OF AUGUST 21:

Location Date Time of Day Details
US 95/Rancho Dr 8/7 9/15 24/7 Ramp Closure: US 95 southbound off-ramp to Rancho Dr closed
Rancho Dr 8/7 – 9/15 24/7 Intermittent closure of right lane of southbound Rancho Dr near US 95 overpass
Sidewalk closed on west side of Rancho Dr between Mesquite Ave and Bonanza Rd at the US 95 overpass
I-15/Charleston Blvd Ongoing Night Lane restrictions on I-15 northbound off-ramp to Charleston westbound
Charleston Blvd Ongoing Night Lane restrictions on eastbound Charleston Blvd, I-15 to Grand Central Pkwy
Lane restrictions on westbound Charleston Blvd, Grand Central Pkwy to MLK Blvd
8/22 – 8/25 Night Lane restrictions on westbound Charleston Blvd, MLK Blvd to Shadow Ln
Grand Central Pkwy Ongoing Night Lane restrictions on southbound and/or northbound Grand Central Pkwy, LV Premium Outlet Dr to Charleston Blvd
Alta Blvd/MLK Blvd 8/21 – 8/25 Night Lane restrictions on eastbound and westbound Alta Blvd, MLK Blvd to I-15
8/21 – 8/25 Night Lane restrictions on northbound MLK Blvd at Alta Blvd
Desert Ln 8/21 Night Lane restrictions on Desert Ln, Ellis Ave to Charleston Blvd
Western Ave/Wall St 8/18 – Ongoing 24/7 Traffic Switch: Intersection of Wall St/Western Ave moving to temporary configuration just south of current intersection
8/21 -8/23 Night Lane restrictions on Western Ave and Wall St at intersection
MLK Blvd/Pinto 8/22 – 8/23 Night Right lane of southbound MLK Blvd closed between Pinto Ln and Hastings Ave
MLK Blvd/US 95 8/23 Day Shoulder closures on MLK Blvd on-ramp to US 95 northbound
Ongoing Night Lane restrictions on MLK Blvd on-ramp to US 95 northbound
Lane restrictions on northbound MLK Blvd off-ramp from I-15/US 95
Lane restrictions on northbound and southbound MLK Blvd near US 95
Symphony Park Ave 8/21 Night Lane restrictions on Symphony Park Ave, MLK Blvd to I-15
Desert Ln 8/21 Night Lane restrictions on Desert Ln between Charleston Blvd and Hastings Ave

 

Upcoming Work

MLK Blvd/US 95 9/6 – 11/15 24/7 Ramp Closure: MLK Blvd on-ramp to US 95 northbound closed
US 95 SB/I-15 SB 9/16 – 9/18 24/7 Ramp Closure: Ramp from US 95 southbound to I-15 southbound closed
Industrial Rd 9/1 – 9/2 Day Lane restrictions on Industrial Rd at Utah Ave
Desert Ln/Ellis TBD Day Lane restrictions on Desert Ln, Ellis Ave to Charleston Blvd

Night work hours are generally 9pm – 6am

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, WEEK OF AUGUST 14:

Location Date Time of Day Details
US 95/Rancho Dr 8/7 9/15 24/7 Ramp Closure: US 95 southbound off-ramp to Rancho Dr closed
Rancho Dr 8/7 – 9/15 24/7 Right lane of southbound Rancho Dr closed near US 95 overpass
Sidewalk closed on west side of Rancho Dr between Mesquite Ave and Bonanza Rd at the US 95 overpass
I-15 NB/US 95 NB 8/14 Night Right lane of I-15 northbound ramp to US 95 northbound closed
I-15/Charleston Blvd Ongoing Night Lane restrictions on I-15 northbound off-ramp to Charleston westbound
Charleston Blvd Ongoing Night Lane restrictions on eastbound Charleston Blvd, I-15 to Grand Central Pkwy
Lane restrictions on westbound Charleston Blvd, Grand Central Pkwy to MLK Blvd
Grand Central Pkwy Ongoing Night Lane restrictions on southbound and/or northbound Grand Central Pkwy, LV Premium Outlet Dr to Charleston Blvd
Alta Blvd 8/14 – 8/18 Night Lane restrictions on eastbound and westbound Alta Blvd, MLK Blvd to I-15
Symphony Park Ave 8/17 Night Lane restrictions on Symphony Park Ave, MLK Blvd to I-15
Western Ave 8/14 – 8/18 Night Lane restrictions on Western Ave, Wyoming to Wall St
Western Ave/Wall St 8/14 – 8/21 Night Lane restrictions near intersection of Western Ave and Wall Street
MLK Blvd/US 95 Ongoing Night Lane restrictions on MLK Blvd on-ramp to US 95 northbound
Lane restrictions on northbound MLK Blvd off-ramp from I-15/US 95
Lane restrictions on northbound and southbound MLK Blvd near US 95

 

Upcoming Work

MLK Blvd/US 95 9/6 – 11/15 24/7 Ramp Closure: MLK Blvd on-ramp to US 95 northbound closed
Western Ave/Wall St 8/21 – Ongoing Night Traffic Switch: Intersection of Wall St/Western Ave moving to temporary configuration just south of current intersection
Desert Ln 8/21 Night Lane restrictions on Desert Ln, Ellis Ave to Charleston Blvd
MLK Blvd/Pinto 8/22 Night Right lane of southbound MLK Blvd closed between Pinto Ln and Hastings Ave
Charleston Blvd 8/22 – 8/25 Night Lane restrictions on westbound Charleston Blvd, MLK Blvd to Shadow Ln
Symphony Park Ave 8/28 – 10/6 Night Lane restrictions on Symphony Park Ave, MLK Blvd to I-15
Industrial Rd TBD Day Lane restrictions on Industrial Rd at Utah Ave
Ellis Ave TBD Day Lane restrictions on Ellis Ave, Desert Ln to Shadow Ln
Desert Ln/Ellis TBD Day Lane restrictions on Desert Ln, Ellis Ave to Charleston Blvd

Night work hours are generally 9pm – 6am

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, WEEK OF AUGUST 7:

Location Date Time of Day Details
US 95/Rancho Dr 8/7 9/15 24/7 Ramp Closure: US 95 southbound off-ramp to Rancho Dr closed
US 95 8/11 Night Temporary right lane closures of US 95 southbound in various locations before Rancho Dr off-ramp
Rancho Dr 8/7 – 9/15 24/7 Right lane of southbound Rancho Dr. closed near US 95 overpass.
24/7 Sidewalk closed on west side of Rancho Dr between Mesquite Ave and Bonanza Rd at the US 95 overpass.
I-15/Charleston Ongoing Night Lane restrictions on I-15 northbound off-ramp to Charleston westbound
Charleston Blvd Ongoing Night Right lane of eastbound Charleston Blvd closed, I-15 to Grand Central Pkwy
Ongoing Night Lane restrictions on westbound Charleston Blvd, Grand Central Pkwy to MLK Blvd
Grand Central Pkwy Ongoing Night Lane restrictions on southbound and/or northbound Grand Central Pkwy, LV Premium Outlet Dr to Charleston Blvd
Western Ave/Wall St 8/8 Night Lane restrictions on westbound Wall St
8/8 Night Lane restrictions on southbound Western Ave at Wall St
MLK Blvd/Oakey Blvd 8/8 – 8/11 Night Right shoulder of northbound MLK Blvd closed from Oakey Blvd to Wall St
MLK Blvd/US 95 8/7 – Ongoing Night Lane restrictions on MLK Blvd on-ramp to US 95 northbound
8/7 – Ongoing Night Lane restrictions on MLK Blvd off-ramp from I-15/US 95
8/8 – Ongoing Night Lane restrictions on northbound and southbound MLK Blvd near US 95

 

Upcoming Work

MLK Blvd/US 95 8/14 – 8/15 Night Lane restrictions on northbound and southbound MLK Blvd near US 95
8/15 – Ongoing Night Right lane of northbound MLK Blvd closed at off-ramp from I-15
8/28 – 9/9 Night Lane restrictions on MLK Blvd on-ramp to US 95 northbound
Alta Blvd 8/14 – 8/18 Night Lane restrictions on eastbound and westbound Alta Blvd, MLK Blvd to I-15
Western Ave 8/14 – 8/18 Night Lane restrictions on Western Ave, Wyoming to Wall St
Desert Ln/Ellis 8/17 – 8/18 Night Lane restrictions on Desert Ln at Ellis
Western Ave/Wall St 8/21 – Ongoing Night Traffic Switch: Intersection of Wall St/Western Ave moving to temporary configuration just south of current intersection
MLK Blvd/Pinto 8/22 – 8/23 Right lane of southbound MLK Blvd closed between Pinto Ln and Hastings Ave
Industrial Rd TBD Day Lane restrictions on S. Industrial Rd at W. Utah Ave
Ellis Ave TBD Day Lane restrictions on Ellis Ave between Desert and Shadow Ln

Night work hours are generally 9pm – 6am

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, WEEK OF JULY 31:

Activity Number Location Date Time of Day Details
29 I-15/Charleston 7/31–Ongoing Night ·   Lane restrictions on I-15 northbound off-ramp to Charleston westbound
14/30 Charleston Blvd

 

7/31 Night ·   2 right lanes of Charleston Blvd eastbound and westbound closed from MLK Blvd through Grand Central Pkwy.
30 8/1–Ongoing Night ·   Right lane of eastbound Charleston Blvd closed from I-15 through Grand Central Pkwy

·   Lane restrictions on westbound Charleston Blvd, Grand Central Pkwy to MLK Blvd

14
5,6 8/4 Night ·   Intermittent closure of Charleston Blvd eastbound and westbound at Grand Central Pkwy.
35, 41 Grand Central Pkwy 7/31–Ongoing Night ·  Lane restrictions on southbound and/or northbound Grand Central Pkwy, Iron Horse Loop to Charleston Blvd
20 Western Ave 7/31–Ongoing Day ·  Lane restrictions on southbound Western Ave at Wall St
42 MLK Blvd/US 95 7/31 Night ·  Right lane and shoulder of MLK Blvd on-ramp to US 95 northbound closed
43 8/1 Night ·  Left lane and shoulder of MLK Blvd on-ramp to US 95 northbound closed
46 MLK Blvd/Pinto 8/2 Night ·  Right lane of southbound MLK Blvd closed before Pinto
16 Shadow Ln 8/4 Night ·  Lane restrictions on Shadow Ln south of Charleston Blvd

 

Upcoming Work

44 US 95/Rancho Dr 8/7 9/15 24/7 ·  Ramp Closure: US 95 southbound off-ramp to Rancho Dr closed
48 MLK Blvd/Oakey Blvd 8/7 – 8/11 Night ·  Right shoulder of northbound MLK Blvd closed from Oakey Blvd to Wall St
49 8/14 – 8/17 Night ·  Lane restrictions on southbound MLK Blvd from Wall St to Oakey Blvd
43 MLK Blvd/US 95 8/10 – 8/12, 8/14 – 8/29 Night ·  Left lane of MLK Blvd on-ramp to US 95 northbound closed
1 8/12, 14, 15 Night ·  Right lane of southbound MLK Blvd closed at on-ramp to US 95 northbound
3 8/15 Night ·  Right lane of northbound MLK Blvd closed at off-ramp from I-15
47 Industrial Rd TBD Day ·  Lane restrictions on S. Industrial Rd at W. Utah Ave
36 Charleston Blvd TBD Night ·  One left turn lane from eastbound Charleston Blvd to Grand Central Pkwy closed
15 Ellis Ave TBD Day ·  Lane restrictions on Ellis Ave between Desert and Shadow Ln

Night work hours are generally 9pm – 6am

 

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, WEEK OF JULY 24:

Activity Number Location Date Time of Day Details
38/39 US 95/Rancho Dr 7/24 Night ·  Right shoulder of southbound US 95 off-ramp to Rancho Dr closed

·  Two right lanes of southbound Rancho Dr closed from US 95 to Mesquite Ave

29 I-15/Charleston 7/24 to 29 Night ·   Lane restrictions on I-15 northbound off-ramp to Charleston westbound
14/30/45 Charleston Blvd 7/24 to 29 Night ·   Right lane of eastbound Charleston Blvd closed from I-15 through Grand Central Pkwy

·   Lane restrictions on westbound Charleston Blvd, Grand Central Pkwy to MLK Blvd

7/26 Night Right lane of Charleston Blvd closed west of MLK Blvd
35/41 Grand Central Pkwy 7/24 to 29 Night ·   Lane restrictions on southbound and/or northbound Grand Central Pkwy, Iron Horse Loop to Charleston Blvd
31 MLK/US 95 7/25 Night Two right lanes of northbound MLK Blvd closed from Mineral Ave to Bonanza Rd
20 Western Ave 7/26 to 29 Day Lane restrictions on southbound Western Ave at Wall St
16 Shadow Ln 7/28 Night Lane restrictions on Shadow Ln south of Charleston Blvd

 

Upcoming Work

44 US 95/Rancho Dr 8/7 to 9/15 24/7 Ramp Closure: US 95 southbound off-ramp to Rancho Dr closed
36 Charleston Blvd TBD Night One left turn lane from eastbound Charleston Blvd to Grand Central Pkwy closed
15 Ellis Ave TBD Day Lane restrictions on Ellis Ave between Desert and Shadow Ln
42 MLK/US 95 7/31 Night Right lane and shoulder of MLK Blvd on-ramp to US 95 northbound closed
43 8/1 Night Left lane and shoulder of MLK Blvd on-ramp to US 95 northbound closed

Night work hours are generally 9pm – 6am

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, WEEK OF JULY 17:

Activity Number Date Time of Day Location Information
31 7/17 and 7/19 Night MLK Blvd Two right lanes of northbound MLK Blvd closed from Mineral Ave to Bonanza Rd
32 7/17 Night Charleston Blvd Lane restriction in far right lane westbound between railroad tracks and Grand Central Pkwy
26 7/17 to 7/20 Night Grand Central Pkwy Lane restrictions on southbound Grand Central Pkwy from Iron Horse Loop to Charleston Blvd
41 7/18 to 7/22 Night Grand Central Pkwy Single right lane of northbound Grand Central Pkwy closed from Charleston Blvd to Iron Horse Loop
33 7/18 Night Charleston Blvd Two right lanes of westbound Charleston Blvd closed from MLK Blvd to Shadow Ln
30 7/18 to 7/22 Night Charleston Blvd Right lane of eastbound Charleston Blvd closed from I-15 through Grand Central Pkwy
29 7/18 to 7/22 Night I-15/Charleston Lane restrictions on I-15 northbound off-ramp to Charleston westbound
14 7/18 to 7/22 Night Charleston Blvd Two right lanes of westbound Charleston Blvd closed from Grand Central Pkwy to MLK Blvd
34 7/20 Night Charleston Blvd Two right lanes of westbound Charleston Blvd closed from Commerce to Grand Central Pkwy
35 7/20 to 7/22 Night Grand Central Pkwy Two right lanes of southbound Grand Central Pkwy closed from Iron Horse Loop to Charleston Blvd
36 Upcoming Night Charleston Blvd One left turn lane from eastbound Charleston Blvd to Grand Central Pkwy closed
38 Upcoming Night US 95/Rancho Dr Right shoulder of southbound US 95 off-ramp to Rancho Dr closed
39 Upcoming Night Rancho Dr Two right lanes of southbound Rancho Dr closed from US 95 to Mesquite Ave
37 Upcoming Night Grand Central Pkwy Left lane restrictions on northbound and southbound Grand Central Pkwy near Iron Horse Loop
40 Upcoming Night Grand Central Pkwy Left lane of southbound Grand Central Pkwy closed from Iron Horse Loop to Charleston Blvd
16 Upcoming Night Shadow Ln Lane restrictions on Shadow Ln south of Charleston Blvd

Night work hours are generally 9pm – 6am

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, WEEK OF JULY 10:

 

Location: I-15 northbound exit to Charleston westbound

Schedule: Night work, Sunday, 7/10, 9 pm to 6 am

Work: Barrier placement

Impacts: RAMP CLOSURE: I-15 northbound off-ramp to Charleston westbound (and Grand Central Pkwy) CLOSED.

 

Location: Grand Central Pkwy at Charleston Blvd and Charleston Blvd at Grand Central Pkwy

Schedule: Night work, Sunday, 7/10, 9 pm to 6 am

Work: Barrier placement

Impacts: Two right lanes closed on southbound Grand Central Pkwy from Iron Horse Loop to Charleston. Two right lanes closed on westbound Charleston from Grand Central Pkwy to MLK Blvd.

 

Location: I-15 northbound exit to Charleston westbound

Schedule: Night work, July 11 – 22, 10 pm to 5 am

Work: Tree removal and locating of utilities

Impacts: Lane restrictions on I-15 northbound off-ramp to Charleston westbound

 

Location: Grand Central Pkwy at Charleston Blvd

Schedule: Night work, July 11 – 22, 10 pm to 5 am

Work: Tree removal and locating of utilities

Impacts: Lane restrictions on southbound Grand Central Pkwy from Iron Horse Loop to Charleston.

 

Location:  Charleston Blvd at Grand Central Pkwy

Schedule: Night work, July 11 – 22, 10 pm to 5 am

Work:  Truck access to construction site

Impacts: Two right lanes of westbound Charleston Blvd closed from I-15 to Grand Central Pkwy

 

Location:  Charleston Blvd at Grand Central Pkwy

Schedule: Night work, July 11 – 13, 10 pm to 5 am

Work:  Locating of utilities

Impacts: Right lane of eastbound Charleston Blvd closed from I-15 Eastbound off ramp through Grand Central Pkwy.

 

Location: Alta/Bonneville from Desert Ln to just east of I-15

Schedule: Night work, Tuesday, 7/12, 10 pm to 5 am

Work: Locating of utilities

Impacts: Left lane of eastbound Alta/Bonneville closed and turn lane to northbound MLK Blvd closed.

 

Location: Charleston Blvd at Shadow Ln

Schedule: Night work, Thursday, 7/14, 10 pm to 5 am

Work: Locating of utilities

Impacts: Two right lanes closed on Charleston Blvd eastbound and westbound at Shadow Ln

 

ADJACENT PROJECT: US 95 REPAIRS

Location: Casino Center on-ramp to US 95 northbound

Work: Button replacement

Schedule: Night work, Monday, 7/11, 10 pm to 5 am

Impacts: RAMP CLOSURE: The Casino Center Blvd on-ramp to US 95 northbound will be CLOSED.

 

UPCOMING ACTIVITIES:

 

Location: Shadow Ln south of Charleston Blvd

Schedule: Night work, 7/17, 10 pm to 5 am

Work: Locating of utilities

Impacts: Lane restrictions on southbound Shadow Ln, just south of Charleston Blvd

 

Location: Ellis Ave between Shadow Ln and Desert Ln

Schedule: Daytime work, 7/19

Work: Locating of utilities

Impacts: Lane restrictions on south half of Ellis Ave

 

Location: Ellis Ave between Shadow Ln and Desert Ln

Schedule: Daytime work, 7/20

Work: Locating of utilities

Impacts: Lane restrictions on north half of Ellis Ave

 

PROJECT NEON CONSTRUCTION ACTIVITY UPDATES, WEEK OF JULY 3:

 

Location: Southbound Western Ave at Wall St

Schedule: July 5 through August 5

Work: Demolition of slabs, clearing of site, site grading.

Impacts: Lane restrictions on southbound Western Ave at Wall St

 

Location: Bonneville and Grand Central Pkwy

Schedule: Night work, Tuesday, 7/5, 10 pm to 5 am

Work: Locating of utilities.

Impacts: Right lane of northbound Grand Central Pkwy closed at Bonneville. Right lane of eastbound Bonneville closed at Grand Central Pkwy.

 

Location: Western Ave, north of Wall St

Schedule: Night work, Wednesday, 7/6, 10 pm to 5 am

Work: Locating of utilities.

Impacts: Lane restrictions on Western Ave just north of Wall St intersection.

 

Location: Grand Central Pkwy at Iron Horse Loop

Schedule: Night work, Thursday, 7/7, 10 pm to 5 am

Work: Locating of utilities.

Impacts: The right lane of southbound Grand Central Pkwy will be closed from Iron Horse Loop to Charleston Blvd.

 

ADJACENT PROJECT: US 95 REPAIRS

Location: US 95 northbound from Eastern Ave to the Spaghetti Bowl

Work: Reflectivity testing and button replacement

Schedule: Night work, Thursday, 7/7, 10 pm to 5 am

Impacts: The far left lane and the far right lane of US 95 northbound will be closed alternately for about 2 hours each.

 

UPCOMING ACTIVITIES:

 

Location: I-15 northbound exit to Charleston westbound

Schedule: Night work, Monday, 7/11, 10 pm to 5 am

Work: Barrier placement

Impacts: Lane restrictions on I-15 northbound off-ramp to Charleston westbound

 

Location: Grand Central Pkwy at Charleston Blvd

Schedule: Night work, Monday, 7/11, 10 pm to 5 am

Work: Barrier placement

Impacts: Lane restrictions on southbound Grand Central Pkwy from Iron Horse Loop to Charleston. Lane restrictions on westbound Charleston, west of Grand Central Pkwy.

 

Location: Grand Central Pkwy at Charleston Blvd

Schedule: Night work, Monday and Tuesday, 7/11 and 7/12, 10 pm to 5 am

Work: Locating of utilities.

Impacts: Lane restrictions on southbound Grand Central Pkwy from Iron Horse Loop to Charleston. Lane restrictions on westbound Charleston from Grand Central Pkwy to MLK Blvd.

 

Location: Charleston Blvd from Commerce to MLK Blvd.

Schedule: Night work, Wednesday and Thursday, 7/13 and 7/14, 10 pm to 5 am

Work: Locating of utilities.

Impacts: Two right lanes closed on Charleston Blvd westbound from Commerce to MLK Blvd.

 

Location: Charleston Blvd at Shadow Ln

Schedule: Night work, Sunday, 7/17, 10 pm to 5 am

Work: Locating of utilities.

Impacts: Two right lanes closed on Charleston Blvd eastbound and westbound at Shadow Ln

 

Location: Shadow Ln south of Charleston Blvd

Schedule: Night work, Monday, 7/18, 10 pm to 5 am

Impacts: Lane restrictions on southbound Shadow Ln, just south of Charleston Blvd

 

Location: Ellis Ave between Shadow Ln and Desert Ln

Schedule: Daytime work, 7/19

Work: Locating of utilities.

Impacts: Lane restrictions on south half of Ellis Ave

 

Location: Ellis Ave between Shadow Ln and Desert Ln

Schedule: Daytime work, 7/20

Work: Locating of utilities.

Impacts: Lane restrictions on north half of Ellis Ave

PROJECT NEON PRE-CONSTRUCTION ACTIVITY UPDATES, WEEK OF JUNE 26:

 

Location: I-15 off-ramp to MLK Blvd

Work: Drain inlet cleaning

Schedule: Night work. Sunday, 6/26, 10 pm to 5 am

Impacts: Lane restrictions on I-15 off ramp to MLK Blvd

 

Location: Charleston Blvd westbound, west of Desert Ln

Work: Demolition of structure

Schedule: Night work. Tuesday, 6/28, 10 pm to 5 am

Impacts: Westbound Charleston, right lane closed near Desert Ln

 

Location: Charleston Blvd eastbound from Shadow to Commerce

Work: Locating of utility lines

Schedule: Night work. Tuesday, 6/28, 10 pm to 5 am

Impacts: Center lane and right lane closed on Charleston Blvd eastbound between Shadow Ln and Commerce

 

Location: MLK Blvd at on-ramp to US 95 southbound and I-15 northbound

Work: Locating of utility lines

Schedule: Night work. Wednesday, 6/29, 10 pm to 5 am

Impacts: Ramp closure: On-ramp from MLK Blvd to US 95 SB and I-15 NB closed

 

Location: I-15 northbound ramp to US 95 northbound

Work: Survey

Schedule: Night work, Wednesday, 6/29, 3 am to 5 am

Impacts: Left lane of I-15 northbound ramp to US 95 northbound closed

 

Location: Wall St. between MLK Blvd and Western Ave

Work: Locating of utility lines

Schedule: Night work. Thursday, 6/30, 10 pm to 5 am

Impacts: Lane restrictions on Wall St between MLK Blvd and Western Ave. Lane restrictions on Western Ave north of Wall St

 

PROJECT NEON PRE-CONSTRUCTION ACTIVITY UPDATES, WEEK OF JUNE 19:

 

Location: Western Avenue between Sahara Ave and Charleston Blvd

Work: Southwest Gas utility work

Schedule: Night work, started Sunday (6/5) and will continue through approximately June 27, 9pm-5am

Impacts: Minor lane restrictions on Western Avenue in both directions between Sahara Ave and Charleston Blvd

 

Location: 1024 Desert Ln. and 1522 W. Charleston Blvd.

Work: Demolition of structures

Schedule: Daytime work, Monday through Friday (6/20 – 6/24)

Impacts: No traffic impacts.

 

 

Adjacent Project: U.S. 95 (I-515) Highway Repairs

Location: U.S. 95 NB between Eastern Ave and the Spaghetti Bowl interchange

Work: Highway repairs, final striping

Schedule: Night work, Tuesday night (6/21)

Impacts: From roughly 10 p.m. to 5 a.m. the right lane of US 95 northbound will be closed (between Las Vegas Blvd and the Spaghetti Bowl) and the Casino Center on-ramp to US 95 northbound will be closed.

 

 

PROJECT NEON PRE-CONSTRUCTION ACTIVITY UPDATES, WEEK OF JUNE 12:

 

Location: Western Avenue between Sahara Ave and Charleston Blvd

Work: Southwest Gas utility work

Schedule: Night work, started Sunday (6/5) and will continue through approximately June 25, 9pm-5am

Impacts: Minor lane restrictions on Western Avenue in both directions between Sahara Ave and Charleston Blvd

 

Location: 1007 S. MLK Blvd

Work: Demolition of structure

Schedule: Daytime work, Monday through Friday (6/13 – 6/17)

Impacts: No traffic impacts. Trucks entering and exiting from Desert Ln.

 

 

Adjacent Project: U.S. 95 (I-515) Highway Repairs

Location: U.S. 95 NB between Eastern Ave and the Spaghetti Bowl interchange

Work: Highway repairs

Schedule: 24 hours/day, Sunday night through Saturday morning, through June 21

Impacts: Traffic on US 95 (I-515) northbound between Las Vegas Boulevard and the Spaghetti Bowl remains split into the two outside lanes with repairs being performed in the middle. The left hand lane will take drivers to US 95 northbound. The right hand lane will take drivers to I-15 North, I-15 South or US 95 Northbound. The Las Vegas Boulevard on-ramp to US 95 northbound is also closed during this time.

* Thursday night, June 16: The Las Vegas Blvd on-ramp will reopen, and the Casino Center on-ramp to U.S. 95 northbound will close.

 

* Friday morning, June 17: All lanes on U.S. 95 will be open to traffic. Lanes will be reduced again Friday night for final striping.

 

* Saturday morning, June 18: All lanes on U.S. 95 will be open and the Casino Center on-ramp will open, marking completion of these repairs.

PROJECT NEON PRE-CONSTRUCTION ACTIVITY UPDATES, WEEK OF JUNE 5:

Location: Western Avenue between Sahara Ave and Charleston Blvd
Work: Southwest Gas utility work
Schedule: Night work, started Sunday (6/5) and will continue for approximately three weeks, 9pm-5am
Impacts: Minor lane restrictions on Western Avenue in both directions between Sahara Ave and Charleston Blvd

Location: U.S. 95 NB and SB at Rancho Dr Interchange
Work: Survey
Schedule: Night work, Monday (6/6), 9pm-5am
Impacts: Minor lane restrictions on U.S. 95 northbound and southbound at the Rancho Dr Interchange

Location: Alta Dr, just east of Desert Ln
Work: Utility trenching
Schedule: Night work, Monday-Tuesday (6/6-6/7), 9pm-4am
Impacts: Minor lane restrictions across Alta Dr just east of Desert Ln

Location: U.S. 95 NB and SB in the Spaghetti Bowl
Work: Survey
Schedule: Night work, Tuesday (6/7), 9pm-5am
Impacts: Minor lane restrictions on U.S. 95 northbound and southbound in the Spaghetti Bowl Interchange

Location: Oakey Blvd westbound between Western Ave and Kiltie Way
Work: Groundwater samples
Schedule: Night work, Wednesday (6/8), 9pm-5am
Impacts: Minor lane restrictions on Oakey westbound between Western and Kiltie Way

Location: Charleston Blvd eastbound between MLK Blvd and Grand Central Parkway
Work: Locating utilities/sidewalk repair
Schedule: Night work, Wednesday and Thursday (6/8 – 6/9), 9pm-4am
Impacts: 2 Right lanes closed on Charleston eastbound between MLK Blvd and Grand Central Parkway

Location: MLK Blvd northbound under U.S. 95
Work: Locating utilities
Schedule: Night work, Thursday 6/9, 9pm-5am
Impacts: Closure of northbound right lane on MLK under U.S. 95

Location: Northbound MLK Blvd off-ramp from I-15 N, US 95 N, or I-15 S
Work: Drainage work
Schedule: Short-term night work, Thursday, 6/9
Impacts: Closure of right lane of MLK off-ramp

Adjacent Project: U.S. 95 (I-515) Highway Repairs

Location: U.S. 95 NB between Eastern Ave and the Spaghetti Bowl interchange
Work: Highway repairs
Schedule: 24 hours/day, Sunday night through Saturday morning, through the end of June
Impacts: Traffic on US 95 (I-515) northbound between Las Vegas Boulevard and the Spaghetti Bowl remains split into the two outside lanes with repairs being performed in the middle. The left hand lane will take drivers to US 95 northbound. The right hand lane will take drivers to I-15 North, I-15 South or US 95 Northbound. This traffic split will be in place through the end of June. The Las Vegas Boulevard on-ramp to US 95 northbound will also be closed during this time.

PROJECT NEON PRE-CONSTRUCTION ACTIVITY UPDATES (6/4-6/6):

Location: Charleston Blvd between Main St and Grand Central Pkwy
Work: Utility work
Schedule: Night work, Sunday (6/5), 9 p.m. – 5 a.m.
Impacts: Single right lane closure Westbound on Charleston between Main St and Grand Central Pkwy

Location: Western Ave between Sahara and Charleston
Work: Utility work by Southwest Gas
Schedule: Night work, Sunday (6/5) continuing for 3 weeks
Impacts: Minor lane restrictions on Western Ave in both directions between Sahara Ave and Grand Central Pkwy

Location: 7th St at I-515
Work: Utility work related to Active Traffic Management System.
Schedule: Daytime work beginning Monday (6/6) and continuing for approximately 3 weeks
Impacts: Closure of sidewalk on east side of 7th St just north of I-515 viaduct.

Adjacent Project: U.S. 95 (I-515) Highway Repairs

Location: U.S. 95 northbound between Eastern Avenue and the Spaghetti Bowl interchange
Work: Highway repairs
Schedule: 24 hours/day, Sunday night through Saturday morning, through the end of June (temporarily open for Memorial Day weekend)
Impacts: Starting Thursday, June 2, traffic on US 95 (I-515) northbound between Las Vegas Boulevard and the Spaghetti Bowl will be split into the two outside lanes with repairs being performed in the middle. The left hand lane will take drivers to US 95 northbound. The right hand lane will take drivers to I-15 North, I-15 South or US 95 Northbound. This traffic split will be in place through the end of June. The Las Vegas Boulevard on-ramp to US 95 northbound will also be closed during this time.

SPECIAL NOTE: The schedule for the activities above is subject to change based on weather and field conditions.

PROJECT NEON PRE-CONSTRUCTION ACTIVITY UPDATES (6/1-6/3):

Location: MLK Blvd, southbound between Bonanza and U.S. 95
Work: Utility potholing
Schedule: Night work, Wednesday (6/1), 9 p.m. – 4 a.m.
Impacts: 1 lane closed on MLK Blvd. southbound between Bonanza and U.S. 95

Location: Charleston Blvd, eastbound between I-15 and Grand Central Parkway
Work: Utility work
Schedule: Night work, Thursday (6/2)
Impacts: 2 lanes closed on Charleston eastbound between I-15 and Grand Central Parkway

Location: I-15/Sahara SB off-ramp and NB on-ramp
Work: Survey work
Schedule: Night work, 10pm-5am, Thursday night (6/2)
Impacts: Minor lane restrictions on I-15/Sahara SB off-ramp and NB on-ramp

Location: I-15 NB, Sahara to Bonneville
Work: Survey work
Schedule: Night work, 10 p.m.-5 a.m., Thursday (6/2)
Impacts: Minor lane restrictions on I-15 NB from Sahara to Bonneville

Location: I-15, just south of Sahara Interchange
Work: Survey work
Schedule: Night work, 10 p.m.-5 a.m., Thursday (6/2)
Impacts: Brief lane reduction of inside lane, both NB and SB

Location: I-15 NB MLK off-ramp
Work: Survey work
Schedule: Night work, 10pm-5am, including a 1-hour ramp closure, Thursday (6/2)
Impacts: Minor lane restrictions on ramps from I-15 NB to U.S. 95 NB and SB and a short-term (1 hr.) night-time ramp closure of off-ramp to MLK

Adjacent Project: U.S. 95 (I-515) Highway Repairs

Location: U.S. 95 northbound between Eastern Avenue and the Spaghetti Bowl interchange
Work: Highway repairs
Schedule: 24 hours/day, Sunday night through Saturday morning, through the end of June (temporarily open for Memorial Day weekend)
Impacts: Starting Thursday, June 2, traffic on US 95 (I-515) northbound between Las Vegas Boulevard and the Spaghetti Bowl will be split into the two outside lanes with repairs being performed in the middle. The left hand lane will take drivers to US 95 northbound. The right hand lane will take drivers to I-15 North, I-15 South or US 95 Northbound. This traffic split will be in place through the end of June. The Las Vegas Boulevard on-ramp to US 95 northbound will also be closed during this time.

SPECIAL NOTE: The schedule for the activities above is subject to change based on weather and field conditions.

If you missed our public meeting on Thursday, May 12, displays and handout materials from the meeting are now available on our project website under Read our latest news>Meetings and Presentations.

PROJECT NEON PRE-CONSTRUCTION ACTIVITIES, WEEK OF MAY 29:

Location: Grand Central Pkwy and Charleston Blvd WB off-ramp (from I-15 North)
Work: Utility work
Schedule: Night work, 9pm-5am, Tuesday (5/31)
Impacts: Grand Central Pkwy: Lane restrictions NB between Charleston Blvd and Iron Horse Loop; Charleston Blvd WB off-ramp (from I-15 north): Minor restrictions in center lane (ramp still open and no restrictions to either right or straight travel movements)

Location: Alta Dr. at Desert Ln.
Work: Utility trenching
Schedule: Night work, 9pm-5am, Wednesday (6/1) and Thursday (6/2)
Impacts: Minor lane restrictions on Alta, east and west of Desert Lane intersection

Location: I-15/Sahara SB off-ramp and NB on-ramp
Work: Potholing Utility Locations
Schedule: Night work, 10pm-5am, Wednesday night (5/25)
Impacts: Lane reductions on Charleston Blvd between MLK and Grand Central Pkwy

Location: I-15 NB, Sahara to Bonneville
Work: Survey work
Schedule: Night work, 10 p.m.-5 a.m., Thursday (6/2)
Impacts: Minor lane restrictions on I-15 NB from Sahara to Bonneville

Location: I-15 NB MLK off-ramp
Work: Survey work
Schedule: Night work, 10pm-5am, including a 1-hour ramp closure, Thursday (6/2)
Impacts: Minor lane restrictions on ramps from I-15 NB to U.S. 95 NB and SB and a short-term (1 hr.) night-time ramp closure of off-ramp to MLK

Adjacent Project: U.S. 95 (I-515) Highway Repairs

Location: U.S. 95 northbound between Eastern Avenue and the Spaghetti Bowl interchange
Work: Highway repairs
Schedule: 24 hours/day, Sunday night through Saturday morning, through the end of June (temporarily open for Memorial Day weekend)
Impacts: Starting Wednesday, June 1, traffic on US 95 (I-515) northbound between Las Vegas Boulevard and the Spaghetti Bowl will be split into the two outside lanes with repairs being performed in the middle. The left hand lane will take drivers to US 95 northbound. The right hand lane will take drivers to I-15 North, I-15 South or US 95 Northbound. This traffic split will be in place through the end of June. The Las Vegas Boulevard on-ramp to US 95 northbound will also be closed during this time.

SPECIAL NOTE: The schedule for the activities above is subject to change based on weather and field conditions.

If you missed our public meeting on Thursday, May 12, displays and handout materials from the meeting are now available on our project website under Read our latest news>Meetings and Presentations.

UPDATED PROJECT NEON PRE-CONSTRUCTION ACTIVITIES, WEEK OF MAY 22:

Location: Charleston Blvd between Grand Central Pkwy and Main St
Work: Potholing for design verification
Schedule: Night work, 9 p.m. – 5 a.m., Tuesday night (5/24)
Impacts: Charleston Blvd EB, left lane closed between Grand Central Pkwy and Main St

Location: I-15 NB and SB between Sahara and Bonanza Rd.
Work: Survey work
Schedule: Night work, 10 p.m. – 5 a.m., Tuesday night (5/24) through Thursday night (5/26)
Impacts: Tuesday night:  Short-term median closures on I-15 NB and SB in various locations between Symphony Park Ave and Bonanza Rd. Wednesday and Thursday nights: Shoulder and right lane closures in various locations on I-15 NB and SB between Symphony Park Ave and Bonanza Rd.

Location: Charleston Blvd
Work: Potholing Utility Locations
Schedule: Night work, 10pm-5am, Wednesday night (5/25)
Impacts: Lane reductions on Charleston Blvd between MLK and Grand Central Pkwy

Location: Grand Central Pkwy
Work: Utility Work
Schedule: Night work, 10pm-5am, Thursday night (5/26)
Impacts: Lane restrictions on I-15 NB off-ramp to Charleston WB, Lane restrictions on NB Grand Central Parkway

Location: 920 and 930 S. MLK
Work: Building demolition
Schedule: Day work, Monday (5/23) through Friday (5/27)
Impacts: No traffic impacts

Adjacent Project: U.S. 95 (I-515) Highway Repairs

Location: U.S. 95 northbound between Eastern Avenue and the Spaghetti Bowl interchange
Work: Highway repairs
Schedule: 24 hours/day, Sunday night through Saturday morning, through the end of June (temporarily open for Memorial Day weekend)
Impacts: U.S. 95 northbound remains reduced to two lanes and the Las Vegas Blvd. on-ramp to U.S. 95 NB remains closed. Repairs to U.S. 95 in this area are scheduled to be complete by the end of June. All lanes and ramps will temporarily reopen for one week over the upcoming holiday weekend beginning Tuesday morning, May 24, at 5 a.m. until Tuesday night, May 31, at 10 p.m.

SPECIAL NOTE: The schedule for the activities above is subject to change based on weather and field conditions.

If you missed our public meeting on Thursday, May 12, displays and handout materials from the meeting are now available on our project website.

PROJECT NEON PRE-CONSTRUCTION ACTIVITIES, WEEK OF MAY 22:

Location: Wall St. between MLK and Western Ave.
Work: Utility Trenching
Schedule: Night work, 10 p.m. – 5 a.m., Sunday night (5/22) and Monday night (5/23)
Impacts: Eastbound and Westbound lane restrictions on Wall St. under I-15 between MLK and Western Ave.

Location: I-15 NB and SB between Sahara and Bonanza Rd.
Work: Survey work
Schedule: Night work, 10 p.m. – 5 a.m., Monday night (5/23) and Tuesday night (5/24)
Impacts: Shoulder and right lane closures in various locations on I-15 NB and SB between Sahara and Bonanza Rd.

Location: Charleston Blvd. West off ramp from I-15 NB
Work: Utility work
Schedule: Night work, 10 p.m. – 5 a.m., Wednesday night (5/25) and Thursday night (5/26)
Impacts: Single lane closure on I-15 NB to Charleston West off ramp. Exit to Grand Central will remain open.

Location: 920 and 930 S. MLK
Work: Building demolition
Schedule: Day work, Monday (5/23) through Friday (5/27)
Impacts: No traffic impacts

Adjacent Project: U.S. 95 (I-515) Highway Repairs

Location: U.S. 95 northbound between Eastern Avenue and the Spaghetti Bowl interchange
Work: Highway repairs
Schedule: 24 hours/day, Sunday night through Saturday morning, through the end of June (temporarily open for Memorial Day weekend)
Impacts: U.S. 95 northbound remains reduced to two lanes and the Las Vegas Blvd. on-ramp to U.S. 95 NB remains closed. Repairs to U.S. 95 in this area are scheduled to be complete by the end of June. All lanes and ramps will temporarily reopen for one week over the upcoming holiday weekend beginning Tuesday morning, May 24, at 5 a.m. until Tuesday night, May 31, at 10 p.m.

SPECIAL NOTE: The schedule for the activities above is subject to change based on weather and field conditions.

If you missed our public meeting on Thursday, May 12, displays and handout materials from the meeting are now available on our project website.

PROJECT NEON PRE-CONSTRUCTION ACTIVITIES, WEEK OF MAY 15:

Location: Charleston Blvd eastbound between Grand Central Parkway and Main Street
Work: Subsurface investigation for design verification of existing railroad bridge
Schedule: Night work, 10pm – 5am, Monday night (5/16) through Thursday night (5/19)
Impacts: Eastbound lane reductions on Charleston between Grand Central Parkway and Main Street

Location: 401 S. MLK Blvd, 920 S. MLK Blvd and 930 S. MLK Blvd
Work: Building demolition
Schedule: Monday 5/16 through Friday 5/20
Impacts: No traffic impacts

Adjacent Project: U.S. 95 (I-515) Highway Repairs

Location: U.S. 95 northbound between Eastern Avenue and the Spaghetti Bowl interchange
Work: Highway repairs
Schedule: 24 hours/day, Sunday night through Saturday morning, through the end of June (temporarily open for Memorial Day weekend)
Impacts: U.S. 95 northbound remains reduced to two lanes. The Las Vegas Boulevard on-ramp to U.S. 95 NB will temporarily reopen Saturday morning, May 14, and close Sunday night, May 15. The mainline lane reduction and closure of the Las Vegas Blvd on-ramp will remain in place until Memorial Day weekend, when they will open temporarily for the holiday weekend. Repairs to U.S. 95 are scheduled to be complete by the end of June.

SPECIAL NOTE: The schedule for the activities above is subject to change based on weather and field conditions.

If you missed our public meeting on Thursday, May 12, displays and handout materials from the meeting will soon be available on our project website.

PROJECT NEON PRE-CONSTRUCTION ACTIVITIES MAY 11:

Location: U.S. 95 at MLK
Work: Survey
Schedule: Wednesday night, 5/11
Impacts: Shoulder work only; no impacts to travel lanes

PROJECT NEON PRE-CONSTRUCTION ACTIVITIES, WEEK OF MAY 8:

Location: 401 S. MLK Blvd and 407 S. MLK Blvd, just north of Alta Drive
Work: Building demolition
Schedule: Monday 5/9 through Friday 5/13
Impacts: Right lane of northbound MLK Blvd, just north of Alta Drive, will be closed Thursday night (5/12), 10pm-5am. This closure will start at the MLK/Alta intersection and extend 500 feet to the north.

Adjacent Project: U.S. 95 (I-515) Highway Repairs
Location: U.S. 95 northbound between Eastern Avenue and the Spaghetti Bowl interchange
Work: Highway repairs
Schedule: 24 hours/day, Sunday night through Saturday morning, through the end of June (temporarily open for Memorial Day weekend)
Impacts: U.S. 95 northbound remains reduced to two lanes through the end of June. The Casino Center (4th Street) on-ramp to U.S. 95 northbound, which is currently closed, will reopen Saturday morning, 5/14. At this time, the Las Vegas Blvd on-ramp to U.S. 95 northbound will be closed.

SPECIAL NOTE: The schedule for the activities above is subject to change based on weather and field conditions.

PROJECT NEON PRE-CONSTRUCTION ACTIVITIES, WEEK OF MAY 1:

Adjacent Project: U.S. 95 (I-515) Highway Repairs
Location: U.S. 95 (I-515) northbound between Eastern Avenue and the Spaghetti Bowl interchange
Work: Highway repairs
Schedule: 24 hours/day, Sunday night through Saturday morning, through the end of June (temporarily open for Memorial Day weekend)
Impacts: U.S. 95 (I-515) northbound reduced to two lanes through the end of June, Casino Center (4th Street) on-ramp to U.S. 95 (I-515) northbound CLOSED until May 11
SPECIAL NOTE: The schedule for the activities above is subject to change based on weather and field conditions.

PROJECT NEON PRE-CONSTRUCTION ACTIVITIES, WEEK OF APRIL 24:

Location: U.S. 95 northbound to MLK Blvd off-ramp
Work: Pre-construction survey
Schedule: Night work, Monday, 4/25, 10pm-5am
Impacts: Off-ramp CLOSED

Location: MLK Blvd to US 95 southbound on-ramp
Work: Pre-construction survey
Schedule: Night work, Tuesday, 4/26, 10pm-5am
Impacts: On-ramp CLOSED

Location: Furniture warehouse on South MLK Boulevard
Work: Demo of slabs and footings; demobilization
Schedule: Night work for demo 7pm-6am, Monday 4/25 – Tuesday 4/26
Impacts: No lane closures

Location: 401 and 920 S. MLK Boulevard
Work: Asbestos abatement
Schedule: Day work, Wednesday 4/27 – Friday 4/29
Impacts: None

Adjacent Project
Location: US 95 (I-515) NB between Eastern Avenue and Spaghetti Bowl.
Work: Highway repair work.
Schedule: 24 hour work, April 28 – May 26 and May 31 – June 29 (End date subject to change)
Impacts: US 95 (I-515) northbound reduced to two lanes.

Location: Casino Center Boulevard on-ramp to US 95 (I-515) northbound.
Work: Highway repair work.
Schedule: 24 hour work, April 28 – May 11
Impacts: Casino Center Boulevard on-ramp to US 95 (I-515) northbound closed. Las Vegas Boulevard on-ramp to US 95 (I-515) open

Location: US 95 (I-515) NB between Eastern Avenue and Spaghetti Bowl.
Work: Traffic Switch
Schedule: Night work, April 28
Impacts: US 95 (I-515) northbound reduced to one lane between 10 p.m. and 5 a.m.
SPECIAL NOTE: The schedule for the activities above is subject to change.

PROJECT NEON PRE-CONSTRUCTION ACTIVITIES, WEEK OF APRIL 17:

Location: Charleston on-ramp to I-15 northbound
Work: Utility potholing for future landscaping
Schedule: Night work, Monday 4/18
Impacts: Shoulder closure

Location: Charleston, eastbound from Commerce to Grand Central Parkway
Work: Utility potholing for future bridge piers
Schedule: Night work, Tuesday 4/19
Impacts: Minor lane closures, eastbound only

Location: Various surface streets throughout project area
Work: Potholing repairs
Schedule: Night work, Wednesday 4/20
Impacts: Very short-term, minor lane restrictions

Location: Furniture warehouse on South MLK Boulevard
Work: Demo of slabs and footings and capping of sewer
Schedule: Night work for demo 7pm-6am, Monday 4/18 – Friday 4/22
Impacts: No lane closures

Location: 401 and 407 S. MLK Boulevard
Work: Asbestos abatement, fire department training, and property demolition
Schedule: Day work: Asbestos abatement 4/18-4/21; fire department training 4/20-4/22; demo 4/22
Impacts: Minimal noise
SPECIAL NOTE: The schedule for these activities is subject to change

Adjacent Project
Location: US 95 (I-515) NB between Eastern Avenue and Spaghetti Bowl, and Las Vegas Boulevard on-ramp to US 95 (I-515) northbound
Work: Highway repair work
Schedule: 24-hour work, April 18 – May 3 (end date subject to change)
Impacts: US 95 (I-515) northbound reduced to two lanes, and Las Vegas Boulevard on-ramp to US 95 (I-515) northbound CLOSED

PROJECT NEON PRE-CONSTRUCTION ACTIVITIES, WEEK OF APRIL 10:

Location: Charleston Blvd between Western Ave and Grand Central Parkway
Work: Utility potholing
Schedule: Night work, Wednesday 4/13 and Thursday 4/14
Impacts: Temporary lane restrictions, eastbound only

Location: Furniture warehouse on South MLK Boulevard
Work: Building demolition
Schedule: Night work 7pm-6am, Monday 4/11 – Friday 4/15
Impacts: No lane closures

Adjacent Project
Location: US 95 (I-515) northbound between Las Vegas Boulevard and Spaghetti Bowl, and Las Vegas Boulevard on-ramp to US 95 (I-515) northbound
Work: Highway repair work
Schedule: Night work, Sunday 4/10 – Friday 4/15
Impacts: US 95 (I-515) northbound reduced to two lanes each night at 7pm, reduced to one lane at 10pm, all lanes open at 6am; Las Vegas Boulevard on-ramp to US 95 (I-515) northbound closed from 7pm-6am each night

PROJECT NEON PRE-CONSTRUCTION ACTIVITIES, WEEK OF APRIL 3:

Location: Alta/Bonneville between Desert Lane and the outlet mall
Work: Pothole repairs
Schedule: Night work, Sunday 4/3
Impacts: Temporary lane restrictions, eastbound and westbound
Location: Oakey Avenue between Kiltie Way and Western Avenue
Work: Pothole repairs
Schedule: Night work, Sunday 4/3
Impacts: Temporary lane restrictions, eastbound and westbound

Location: Furniture warehouse on South MLK Boulevard
Work: Building demolition and utility potholing
Schedule: Removal of roof and walls
Impacts: No lane closures

Adjacent Project
Location: US 95 (I-515) northbound between Las Vegas Boulevard and Spaghetti Bowl, and Las Vegas Boulevard on-ramp to US 95 (I-515) northbound
Work: Highway repair work
Schedule: Night work, Sunday 4/3 – Friday 4/8
Impacts: US 95 (I-515) northbound reduced to two lanes each night at 7pm, reduced to one lane at 11pm, all lanes open at 5am; Las Vegas Boulevard on-ramp to US 95 (I-515) northbound closed from 7pm-5am each night